51. Sea Robin Pipeline Company; Notice of Proposed Changes in FERC Gas Tariff

NOTICES: Sea Robin Pipeline Co.,

December 18, 2002.

Take notice that on December 16, 2002, Sea Robin Pipeline Company (Sea Robin) tendered for filing as part of its FERC Gas Tariff, First Revised Volume No. 1, the following tariff sheet, proposed to be effective January 15, 2003:

Fourth Revised Sheet No. 10

Sea Robin states that this filing is being made to remove the

DEPARTMENT OF ENERGY : Federal Energy Regulatory Commission

52. Texas Gas Transmission Corporation; Notice of Compliance Filing

NOTICES: Texas Gas Transmission Corp.,

December 18, 2002.

Take notice that on December 10, 2002, Texas Gas Transmission Corporation (Texas Gas) tendered for filing as part of its FERC Gas Tariff, First Revised Volume No. 1, Substitute Fifth Revised Sheet No. 40, to become effective November 1, 2002.

Texas Gas states that the purpose of this filing is to submit a corrected tariff

DEPARTMENT OF ENERGY : Federal Energy Regulatory Commission

53. Texas Gas Transmission Corporation; Notice of Compliance Filing

NOTICES: Texas Gas Transmission Corp.,

December 18, 2002.

Take notice that on December 10, 2002, Texas Gas Transmission Corporation (Texas Gas) tendered for filing as part of its FERC Gas Tariff, First Revised Volume No. 1, Substitute Sixth Revised Sheet No. 40, to be effective November 1, 2002.

Texas Gas states that the purpose of this filing is to submit a corrected tariff

DEPARTMENT OF ENERGY : Federal Energy Regulatory Commission

54. Transcontinental Gas Pipe Line Corporation; Notice of Proposed Changes in FERC Gas Tariff

NOTICES: Transcontinental Gas Pipe Line Corp.,

December 18, 2002.

Take notice that on December 12, 2002 Transcontinental Gas Pipe Line Corporation (Transco) tendered for filing as part of its FERC Gas Tariff, Third Revised Volume No. 1, and Original Volume No. 2, the tariff sheets listed Appendix A to the filing, with a proposed effective date of February 1, 2003.

Transco states that

DEPARTMENT OF ENERGY : Federal Energy Regulatory Commission

55. Wayne-White Counties Electric Cooperative, Notice of Application

NOTICES: Wayne-White Counties Electric Cooperative,

December 18, 2002.

Take notice that on December 10, 2002, WayneWhite Counties Electric Cooperative (WayneWhite) submitted an application pursuant to section 204 of the Federal Power Act seeking authorization to make longterm borrowings under a loan agreement with the National Rural Utilities Cooperative Finance Corporation in an amount not to

DEPARTMENT OF ENERGY : Federal Energy Regulatory Commission

56. Industrial Materials for the Future

NOTICES: Industrial Materials for the Future,

The U.S. Department of Energy (DOE), Idaho Operations Office (ID) is seeking applications for costshared research and development of materials or materials processing methods, in accordance with the Program Plan for the Industrial Materials for the Future (IMF). This will be a national effort to research, design, develop, engineer, and test new
DEPARTMENT OF ENERGY : Energy Department

57. Notice Amending Procedures Described in November 12, 2002 Notice

NOTICES: Queuing technical conference,

The Federal Energy Regulatory Commission issued a Notice Of Possible Discussion Items For January 21, 2993 Queuing Technical Conference on December 17, 2002 that included information on the conference and an attachment of possible topics of discussion and instructions on how to participate in the conference.
DEPARTMENT OF ENERGY : Federal Energy Regulatory Commission

58. The New PJM Companies: American Electric Power Service Corporation on behalf of its operating companies Appalachian

NOTICES: American Electric Power Service Corp. et al.,

December 18, 2002.

Take notice that on December 11, 2002, in accordance with section 205 of the Federal Power Act (FPA), American Electric Power Service Corporation on behalf of Appalachian Power Service Company, Columbus Southern Power Company, Indiana Michigan Power Company, Kentucky Power Company, Kingsport Power Company, Ohio Power Company

DEPARTMENT OF ENERGY : Federal Energy Regulatory Commission

59. Columbia Gas Transmission Corporation; Notice of Compliance Filing

NOTICES: Columbia Gas Transmission Corp.,

December 18, 2002.

Take notice that on December 13, 2002, Columbia Gas Transmission Corporation (Columbia) tendered for filing as part of its FERC Gas Tariff, Second Revised Volume No. 1, Seventh Revised Sheet No. 267; Substitute Second Revised Sheet No. 357; and Substitute Fifth Revised Sheet No. 581, proposed effective date of November 15,

DEPARTMENT OF ENERGY : Federal Energy Regulatory Commission

60. Dominion Transmission, Inc.; Notice of Tariff Filing

NOTICES: Dominion Transmission, Inc.,

December 18, 2002.

Take notice that on December 13, 2002, Dominion Transmission, Inc. (DTI) tendered for filing as part of its FERC Gas Tariff, Third Revised Volume No. 1, the following tariff sheet as a correction to its November 21, 2002, filing in which a typographical error occurred and incorrectly listed the GRI Adjustment:
Substitute

DEPARTMENT OF ENERGY : Federal Energy Regulatory Commission

61. Eastern Shore Natural Gas Company; Notice of Tariff Filing

NOTICES: Eastern Shore Natural Gas Co.,

December 18, 2002.

Take notice that on December 13, 2002, Eastern Shore Natural Gas Company (ESNG) tendered for filing as part of its FERC Gas Tariff, Second Revised Volume No. 1, the revised tariff sheets listed in Appendix A to the filing, with a proposed effective date of January 1, 2003.

ESNG states that the purpose of this instant

DEPARTMENT OF ENERGY : Federal Energy Regulatory Commission

62. Docket No. RP03-199-000]

NOTICES: Enbridge Pipelines (AlaTenn) L.L.C.,


Enbridge Pipelines (AlaTenn) L.L.C.; Notice of Tariff Filing December 18, 2002.

Take notice that on December 13, 2002, Enbridge Pipelines (AlaTenn) L.L.C. (AlaTenn) tendered for filing as part of its FERC Gas Tariff, Fourth Revised Volume No. 1, First Revised Sheet No. 113, to be made effective January 1, 2003.

AlaTenn states that the

DEPARTMENT OF ENERGY : Federal Energy Regulatory Commission

63. Enron Europe Operation (Advisor) Limited , et al.; Electric Rate and Corporate Filings

NOTICES: Enron Europe Operation (Advisor) Ltd. et al.,

December 17, 2002.

The following filings have been made with the Commission. The filings are listed in ascending order within each docket
classification.
[[Page 78224]]
1. Enron Europe Operation (Advisor) Limited

[Docket No. EG0328000]

Take notice that on December 11, 2002, Enron Europe Operation (Advisor) Limited (the Applicant), with its

DEPARTMENT OF ENERGY : Federal Energy Regulatory Commission

64. Notice of Application Tendered for Filing With the Commission, and Soliciting Additional Study Requests, and

NOTICES: Hydroelectric applications,

December 17, 2002.

Take notice that the following hydroelectric application has been filed with the Commission and is available for public inspection.

a. Type of Application: Minor original license.

b. Project No.: 12423001.

c. Date filed: November 25, 2002.

d. Applicant: American Falls Reservoir District No. 2 and Big Wood Canal

DEPARTMENT OF ENERGY : Federal Energy Regulatory Commission

65. Notice of Alternative Dispute Resolution Workshop

NOTICES: Alternative dispute resolution workshop,

December 17, 2002.

The Commission's Dispute Resolution Service (DRS) will hold a workshop on alternative dispute resolution and how it can be used during the natural gas pipeline prefiling process. The workshop will be held on January 9, 2003, at the Airport Marriott Hotel, 18700 John F. Kennedy Blvd., Houston, Texas 77032.

The workshop

DEPARTMENT OF ENERGY : Federal Energy Regulatory Commission

66. Notice of FERC Staff Participation at MISO-PJM-SPP Reliability Seams Workshop

NOTICES: MISO-PJM-SPP reliability seams workshop,

December 16, 2002.

The Federal Energy Regulatory Commission hereby gives notice that on December 18, 2002, members of its staff will attend the MISOPJMSPP reliability seams workshop, concerning proposed solutions to address parallel path flow issues and the coordination of congestion management processes and ATC/AFC values between the Midwest

DEPARTMENT OF ENERGY : Federal Energy Regulatory Commission

67. California Independent System Operator Corporation; Notice of Filing

NOTICES: California Independent System Operator Corp.,

December 17, 2002.

Take notice that on November 8, 2002, California Independent System Operator Corporation (ISO) tendered for filing with the Federal Energy Regulatory Commission (Commission) an informational rate filing. The informational filing sets forth the basis for the ISO's GMC rates effective as of January 1, 2003.

Any person

DEPARTMENT OF ENERGY : Federal Energy Regulatory Commission

68. Commonwealth Edison Company and Commonwealth Edison Company of Indiana, Inc.; Notice of Filing

NOTICES: Commonwealth Edison Co. et al.,

December 16, 2002.

Take notice that on December 11, 2002, Commonwealth Edison Company and Commonwealth Edison Company of Indiana, Inc. (collectively ComEd) tendered for filing with the Federal Energy Regulatory Commission (Commission) a notice of cancellation of its Open Access Transmission Tariff (OATT). On either February 1, 2003, or March 1,

DEPARTMENT OF ENERGY : Federal Energy Regulatory Commission

69. Duquesne Light Company; Notice of Filing

NOTICES: Duquesne Light Co.,

December 16, 2002.

Take notice that on December 12, 2002, Duquesne Light Company (DLC) filed a Service Agreement for Retail Network Integration Transmission Service and a Network Operating Agreement for Retail Network Integration Transmission Service dated December 12, 2002, with electricAmerica under DLC's Open Access Transmission Tariff

DEPARTMENT OF ENERGY : Federal Energy Regulatory Commission

70. FirstEnergy Solutions Corp., Complainant v. PJM Interconnection, LLC, Respondent; Edison Mission Energy, Complainant

NOTICES: FirstEnergy Solutions Corp. et al.,

December 17, 2002.

Take notice that on December 11, 2002, PJM Interconnection, LLC (PJM), respondent, filed with the Federal Energy Regulatory Commission (Commission) responses to data requests propounded by the Commission by letter dated November 26, 2002, in the abovecaptioned dockets. Respondent states that it has served a copy of these

DEPARTMENT OF ENERGY : Federal Energy Regulatory Commission

71. Liberty Electric Power, LLC; Notice of Filing

NOTICES: Liberty Electric Power, LLC,

December 17, 2002.

Take notice that on December 13, 2002, Liberty Electric Power, LLC (Liberty) tendered for filing, pursuant to section 205 of the Federal Power Act (16 U.S.C.824d), and part 35 of the Federal Energy Regulatory Commission rules of practice and procedure, an amended rate schedule for reactive power to be provided to the PJM

DEPARTMENT OF ENERGY : Federal Energy Regulatory Commission

72. Mojave Pipeline Company; Notice of Tariff Filing

NOTICES: Mojave Pipeline Co.,

December 16, 2002.

Take notice that on November 27, 2002, Mojave Pipeline Company (Mojave) tendered for filing as part of its FERC Gas Tariff, Second

Revised Volume No. 1, Ninth Revised Sheet No. 11; and Substitute Original Sheet No. 243, with an effective date of January 1, 2003.

Mojave states that the tariff sheets revise the fuel

DEPARTMENT OF ENERGY : Federal Energy Regulatory Commission

73. New York Independent System Operator, Inc.; Notice of Filing

NOTICES: New York Independent System Operator, Inc.,

December 16, 2002.

Take notice that on December 2, 2002, the New York Independent System Operator, Inc. (NYISO) tendered for filing with the Federal Energy Regulatory Commission (Commission) a compliance filing in accordance with the Commission's October 31, 2002, order in the above captioned proceeding.

The NYISO states that it has served a

DEPARTMENT OF ENERGY : Federal Energy Regulatory Commission

74. Tenaska Power Services Co., Complainant, v. Midwest Independent Transmission System Operator, Inc., Respondent;

NOTICES: Tenaska Power Services Co.,

December 16, 2002.

Take notice that on December 10, 2002, Tenaska Power Services Co. (Tenaska Power) tendered for filing with the Federal Energy Regulatory Commission (Commission) a complaint against Midwest Independent Transmission System Operator, Inc. (MISO) alleging MISO has violated its Tariff and Commission precedent and policy by failing

DEPARTMENT OF ENERGY : Federal Energy Regulatory Commission

75. Notice of Intent To Prepare an Environmental Impact Statement and To Conduct Public Scoping Meetings, and Notice of

NOTICES: Moab Uranium Mill Tailings Site, UT; remediation; floodplains and wetlands involvement,

Pursuant to the National Environmental Policy Act of 1969 (NEPA) and the Department of Energy (DOE) NEPA Implementing Procedures (10 CFR part 1021), DOE announces its intent to prepare an Environmental Impact Statement (EIS) to assess the potential environmental impacts of actions that would remediate contaminated soils, tailings, and ground water