NOTICES: Sea Robin Pipeline Co.,
Published: 2002-12-24
December 18, 2002.
Take notice that on December 16, 2002, Sea Robin Pipeline Company
(Sea Robin) tendered for filing as part of its FERC Gas Tariff, First
Revised Volume No. 1, the following tariff sheet, proposed to be effective January 15, 2003:
Fourth Revised Sheet No. 10
Sea Robin states that this filing is being made to remove the
NOTICES: Texas Gas Transmission Corp.,
Published: 2002-12-24
December 18, 2002.
Take notice that on December 10, 2002, Texas Gas Transmission
Corporation (Texas Gas) tendered for filing as part of its FERC Gas
Tariff, First Revised Volume No. 1, Substitute Fifth Revised Sheet No. 40, to become effective November 1, 2002.
Texas Gas states that the purpose of this filing is to submit a
corrected tariff
NOTICES: Texas Gas Transmission Corp.,
Published: 2002-12-24
December 18, 2002.
Take notice that on December 10, 2002, Texas Gas Transmission
Corporation (Texas Gas) tendered for filing as part of its FERC Gas
Tariff, First Revised Volume No. 1, Substitute Sixth Revised Sheet No. 40, to be effective November 1, 2002.
Texas Gas states that the purpose of this filing is to submit a
corrected tariff
NOTICES: Transcontinental Gas Pipe Line Corp.,
Published: 2002-12-24
December 18, 2002.
Take notice that on December 12, 2002 Transcontinental Gas Pipe
Line Corporation (Transco) tendered for filing as part of its FERC Gas
Tariff, Third Revised Volume No. 1, and Original Volume No. 2, the
tariff sheets listed Appendix A to the filing, with a proposed effective date of February 1, 2003.
Transco states that
NOTICES: Wayne-White Counties Electric Cooperative,
Published: 2002-12-24
December 18, 2002.
Take notice that on December 10, 2002, WayneWhite Counties
Electric Cooperative (WayneWhite) submitted an application pursuant to
section 204 of the Federal Power Act seeking authorization to make
longterm borrowings under a loan agreement with the National Rural
Utilities Cooperative Finance Corporation in an amount not to
NOTICES: Industrial Materials for the Future,
Published: 2002-12-24
The U.S. Department of Energy (DOE), Idaho Operations Office
(ID) is seeking applications for costshared research and development
of materials or materials processing methods, in accordance with the
Program Plan for the Industrial Materials for the Future (IMF). This
will be a national effort to research, design, develop, engineer, and
test new
NOTICES: Queuing technical conference,
Published: 2002-12-24
The Federal Energy Regulatory Commission issued a Notice Of
Possible Discussion Items For January 21, 2993 Queuing Technical
Conference on December 17, 2002 that included information on the
conference and an attachment of possible topics of discussion and
instructions on how to participate in the conference.
NOTICES: American Electric Power Service Corp. et al.,
Published: 2002-12-24
December 18, 2002.
Take notice that on December 11, 2002, in accordance with section
205 of the Federal Power Act (FPA), American Electric Power Service
Corporation on behalf of Appalachian Power Service Company, Columbus
Southern Power Company, Indiana Michigan Power Company, Kentucky Power
Company, Kingsport Power Company, Ohio Power Company
NOTICES: Columbia Gas Transmission Corp.,
Published: 2002-12-24
December 18, 2002.
Take notice that on December 13, 2002, Columbia Gas Transmission
Corporation (Columbia) tendered for filing as part of its FERC Gas
Tariff, Second Revised Volume No. 1, Seventh Revised Sheet No. 267;
Substitute Second Revised Sheet No. 357; and Substitute Fifth Revised
Sheet No. 581, proposed effective date of November 15,
NOTICES: Dominion Transmission, Inc.,
Published: 2002-12-24
December 18, 2002.
Take notice that on December 13, 2002, Dominion Transmission, Inc.
(DTI) tendered for filing as part of its FERC Gas Tariff, Third Revised
Volume No. 1, the following tariff sheet as a correction to its
November 21, 2002, filing in which a typographical error occurred and incorrectly listed the GRI Adjustment:
Substitute
NOTICES: Eastern Shore Natural Gas Co.,
Published: 2002-12-24
December 18, 2002.
Take notice that on December 13, 2002, Eastern Shore Natural Gas
Company (ESNG) tendered for filing as part of its FERC Gas Tariff,
Second Revised Volume No. 1, the revised tariff sheets listed in
Appendix A to the filing, with a proposed effective date of January 1, 2003.
ESNG states that the purpose of this instant
NOTICES: Enbridge Pipelines (AlaTenn) L.L.C.,
Published: 2002-12-24
Enbridge Pipelines (AlaTenn) L.L.C.; Notice of Tariff Filing December 18, 2002.
Take notice that on December 13, 2002, Enbridge Pipelines (AlaTenn)
L.L.C. (AlaTenn) tendered for filing as part of its FERC Gas Tariff,
Fourth Revised Volume No. 1, First Revised Sheet No. 113, to be made effective January 1, 2003.
AlaTenn states that the
NOTICES: Enron Europe Operation (Advisor) Ltd. et al.,
Published: 2002-12-23
December 17, 2002.
The following filings have been made with the Commission. The filings are listed in ascending order within each docket
classification.
[[Page 78224]]
1. Enron Europe Operation (Advisor) Limited
[Docket No. EG0328000]
Take notice that on December 11, 2002, Enron Europe Operation
(Advisor) Limited (the Applicant), with its
NOTICES: Hydroelectric applications,
Published: 2002-12-23
December 17, 2002.
Take notice that the following hydroelectric application has been
filed with the Commission and is available for public inspection.
a. Type of Application: Minor original license.
b. Project No.: 12423001.
c. Date filed: November 25, 2002.
d. Applicant: American Falls Reservoir District No. 2 and Big Wood
Canal
NOTICES: Alternative dispute resolution workshop,
Published: 2002-12-23
December 17, 2002.
The Commission's Dispute Resolution Service (DRS) will hold a
workshop on alternative dispute resolution and how it can be used
during the natural gas pipeline prefiling process. The workshop will
be held on January 9, 2003, at the Airport Marriott Hotel, 18700 John F. Kennedy Blvd., Houston, Texas 77032.
The workshop
NOTICES: MISO-PJM-SPP reliability seams workshop,
Published: 2002-12-23
December 16, 2002.
The Federal Energy Regulatory Commission hereby gives notice that
on December 18, 2002, members of its staff will attend the MISOPJMSPP
reliability seams workshop, concerning proposed solutions to address
parallel path flow issues and the coordination of congestion management
processes and ATC/AFC values between the Midwest
NOTICES: California Independent System Operator Corp.,
Published: 2002-12-23
December 17, 2002.
Take notice that on November 8, 2002, California Independent System
Operator Corporation (ISO) tendered for filing with the Federal Energy
Regulatory Commission (Commission) an informational rate filing. The
informational filing sets forth the basis for the ISO's GMC rates effective as of January 1, 2003.
Any person
NOTICES: Commonwealth Edison Co. et al.,
Published: 2002-12-23
December 16, 2002.
Take notice that on December 11, 2002, Commonwealth Edison Company
and Commonwealth Edison Company of Indiana, Inc. (collectively ComEd)
tendered for filing with the Federal Energy Regulatory Commission
(Commission) a notice of cancellation of its Open Access Transmission
Tariff (OATT). On either February 1, 2003, or March 1,
NOTICES: Duquesne Light Co.,
Published: 2002-12-23
December 16, 2002.
Take notice that on December 12, 2002, Duquesne Light Company (DLC)
filed a Service Agreement for Retail Network Integration Transmission
Service and a Network Operating Agreement for Retail Network
Integration Transmission Service dated December 12, 2002, with
electricAmerica under DLC's Open Access Transmission Tariff
NOTICES: FirstEnergy Solutions Corp. et al.,
Published: 2002-12-23
December 17, 2002.
Take notice that on December 11, 2002, PJM Interconnection, LLC
(PJM), respondent, filed with the Federal Energy Regulatory Commission
(Commission) responses to data requests propounded by the Commission by
letter dated November 26, 2002, in the abovecaptioned dockets.
Respondent states that it has served a copy of these
NOTICES: Liberty Electric Power, LLC,
Published: 2002-12-23
December 17, 2002.
Take notice that on December 13, 2002, Liberty Electric Power, LLC
(Liberty) tendered for filing, pursuant to section 205 of the Federal
Power Act (16 U.S.C.824d), and part 35 of the Federal Energy Regulatory
Commission rules of practice and procedure, an amended rate schedule
for reactive power to be provided to the PJM
NOTICES: Mojave Pipeline Co.,
Published: 2002-12-23
December 16, 2002.
Take notice that on November 27, 2002, Mojave Pipeline Company
(Mojave) tendered for filing as part of its FERC Gas Tariff, Second
Revised Volume No. 1, Ninth Revised Sheet No. 11; and Substitute
Original Sheet No. 243, with an effective date of January 1, 2003.
Mojave states that the tariff sheets revise the fuel
NOTICES: New York Independent System Operator, Inc.,
Published: 2002-12-23
December 16, 2002.
Take notice that on December 2, 2002, the New York Independent
System Operator, Inc. (NYISO) tendered for filing with the Federal
Energy Regulatory Commission (Commission) a compliance filing in
accordance with the Commission's October 31, 2002, order in the above captioned proceeding.
The NYISO states that it has served a
NOTICES: Tenaska Power Services Co.,
Published: 2002-12-23
December 16, 2002.
Take notice that on December 10, 2002, Tenaska Power Services Co.
(Tenaska Power) tendered for filing with the Federal Energy Regulatory
Commission (Commission) a complaint against Midwest Independent
Transmission System Operator, Inc. (MISO) alleging MISO has violated
its Tariff and Commission precedent and policy by failing
NOTICES: Moab Uranium Mill Tailings Site, UT; remediation; floodplains and wetlands involvement,
Published: 2002-12-20
Pursuant to the National Environmental Policy Act of 1969
(NEPA) and the Department of Energy (DOE) NEPA Implementing Procedures
(10 CFR part 1021), DOE announces its intent to prepare an
Environmental Impact Statement (EIS) to assess the potential
environmental impacts of actions that would remediate contaminated
soils, tailings, and ground water