1. BP West Coast Products LLC and ExxonMobile Oil Corporation, Complainants v. SFPP, LP, Respondents; Notice of

NOTICES: BP West Coast Products LLC et al.,

December 23, 2004.

Take notice that on December 22, 2004, BP West Coast Products LLC (BP) and ExxonMobil Oil Corporation (ExxonMobile) (collective, Complainants) tendered for filing their Fourth Original Complaint against SFPP, L.P. Complainants allege that SFPP's West Line Watson Vapaor Recovery Charge, Sepulveda Line, North Line, Oregon Line

DEPARTMENT OF ENERGY : Federal Energy Regulatory Commission

2. Elk River Windfarm, Inc., et al.; Electric Rate and Corporate Filings

NOTICES: Electric rate and corporate regulation filings,

December 23, 2004.

The following filings have been made with the Commission. The filings are listed in ascending order within each docket
classification.
1. Elk River Windfarm LLC

[Docket No. EG0525000]

On December 21, 2004, Elk River Windfarm LLC (Elk River), filed an application for determination of exempt wholesale generator status

DEPARTMENT OF ENERGY : Federal Energy Regulatory Commission

3. Parker-Davis Project--Post-2008 Resource Pool

NOTICES: Parker-Davis Project; post-2008 resource pool; power allocation procedures and applications call,

The Western Area Power Administration (Western), a Federal power marketing agency of the Department of Energy (DOE), published a notice of proposed procedures and call for applications, ParkerDavis ProjectPost2008 Resource Pool in the Federal Register on October 1, 2004. This notice extends the filing date for the submission of comments on the
DEPARTMENT OF ENERGY : Western Area Power Administration

4. Indian River Power Supply, LLC; Notice of Competing Application Accepted for Filing With the Commission

NOTICES: Hydroelectric applications,

December 22, 2004.

Take notice that the following hydroelectric application has been filed with the Commission and is available for public inspection.

a. Type of Application: 5MW Exemption.

b. Project No.: 12462000.

c. Date Filed: July 28, 2003.

d. Applicant: Indian River Power Supply, LLC.

e. Name of Project: Indian River.

DEPARTMENT OF ENERGY : Federal Energy Regulatory Commission

5. Crown Landing, LLC; Notice of Technical Conference

NOTICES: Crown Landing, LLC; technical conference,

December 22, 2004.

On Wednesday, January 12, 2005, at 8:30 a.m. (EDT), staff from the Commission's Office of Energy Projects will convene a cryogenic design and technical conference regarding the proposed Crown Landing LNG import terminal. The cryogenic conference will be held at the Holiday Inn Hotel located at One Pureland Drive, Swedesboro,

DEPARTMENT OF ENERGY : Federal Energy Regulatory Commission

6. Gulfterra Texas Pipeline, LP; Notice Of Technical Conference

NOTICES: Gulfterra Texas Pipeline, LP; technical conference,

December 22, 2004.

Take notice that a technical conference will be held on Thursday, January 6, 2005, at 1:30 p.m. (EST), in a room to be designated at the Federal Energy Regulatory Commission, 888 First Street NE, Washington, DC 20426.

The conference will address questions related to the July 12, 2004, filing by Gulfterra Texas Pipeline,

DEPARTMENT OF ENERGY : Federal Energy Regulatory Commission

7. Market Based Rates for Public Utilities; Notice of Technical Conference

NOTICES: Market based rates for public utilities; technical conference,

December 22, 2004.

Take notice that a technical conference will be held concerning issues associated with the abovecaptioned rulemaking proceeding on market based rates. The technical conference will take place on January 27 and 28, 2005, from 9 a.m. to 4:30 p.m. (EST), in the Commission Meeting Room at the Federal Energy Regulatory Commission,

DEPARTMENT OF ENERGY : Federal Energy Regulatory Commission

8. CenterPoint Energy-Mississippi River Transmission Corporation; Notice of Tariff Filing

NOTICES: CenterPoint Energy-Mississippi River Transmission Corp.,

December 22, 2004.

Take notice that on December 20, 2004, CenterPoint Energy Mississippi River Transmission Corporation (MRT) tendered for filing as part of its FERC Gas Tariff, Third Revised Volume No. 1, the tariff sheets listed in Appendix A to the filing, to be effective January 19, 2005.

MRT states that the purpose of this filing is to

DEPARTMENT OF ENERGY : Federal Energy Regulatory Commission

9. Columbia Gas Transmission Corporation; Notice of Tariff Filing

NOTICES: Columbia Gas Transmission Corp.,

December 22, 2004.

Take notice that on December 17, 2004, Columbia Gas Transmission Corporation (Columbia) tendered for filing as part of its FERC Gas Tariff, Second Revised Volume No. 1, the following revised tariff sheets with a proposed date of January 16, 2005:
Seventh Revised Sheet No. 108,
Fourth Revised Sheet No. 196,
Third Revised Sheet

DEPARTMENT OF ENERGY : Federal Energy Regulatory Commission

10. Columbia Gulf Transmission Company; Notice of Tariff Filing

NOTICES: Columbia Gulf Transmission Co.,

December 22, 2004.

Take notice that on December 17, 2004, Columbia Gulf Transmission Company (Columbia Gulf) tendered for filing as part of its FERC Gas Tariff, Second Revised Volume No. 1, the following revised tariff sheets with a proposed date of January 1, 2005:

Thirtysixth Revised Sheet No. 18,

Thirtyseventh Revised Sheet No. 19.

DEPARTMENT OF ENERGY : Federal Energy Regulatory Commission

11. Columbia Gulf Transmission Company; Notice of Tariff Filing

NOTICES: Columbia Gulf Transmission Co.,

December 22, 2004.

Take notice that on December 17, 2004, Columbia Gulf Transmission Company (Columbia Gulf) tendered for filing as part of its FERC Gas Tariff, Second Revised Volume No. 1, the following revised tariff sheets with a proposed date of January 16, 2005:
Second Revised Sheet No. 87,

Third Revised Sheet No. 94.

Columbia Gulf

DEPARTMENT OF ENERGY : Federal Energy Regulatory Commission

12. Columbia Gulf Transmission Company; Notice of Tariff Filing

NOTICES: Columbia Gulf Transmission Co.,

December 22, 2004.

Take notice that on December 17, 2004, Columbia Gulf Transmission Company (Columbia Gulf) pursuant to Section 19.6 of the General Terms and Conditions (GTC) of its FERC Gas Tariff, Second Revised Volume No. 1, filed a Penalty Revenue Crediting Report for the 20032004 contract year.

Any person desiring to intervene or to

DEPARTMENT OF ENERGY : Federal Energy Regulatory Commission

13. Cranberry Pipeline Corporation; Notice of Offer of Settlement

NOTICES: Cranberry Pipeline Corp.,

December 22, 2004.

Take notice that on December 17, 2004, Cranberry Pipeline Corporation (Cranberry) tendered for filing an Offer of Settlement (settlement) in the abovereferenced proceeding. The proposed settlement establishes a systemwide transportation rate of 68.17 cents/Dth pursuant to NGPA section 311(a)(2). The proposed settlement also

DEPARTMENT OF ENERGY : Federal Energy Regulatory Commission

14. Gulfstream Natural Gas System, L.L.C.; Notice of Negotiated Rate

NOTICES: Gulfstream Natural Gas System, L.L.C.,

December 22, 2004.

Take notice that on December 20, 2004, Gulfstream Natural Gas System, L.L.C. (Gulfstream) tendered for filing as part of its FERC Gas Tariff, Original Volume No. 1, Original Sheet No. 8.01l, reflecting an effective date of January 1, 2004.

Gulfstream states that this filing is being made in connection with a negotiated

DEPARTMENT OF ENERGY : Federal Energy Regulatory Commission

15. Iroquois Gas Transmission System, L.P.; Notice of Compliance Filing

NOTICES: Iroquois Gas Transmission System, L.P.,

December 22, 2004.

Take notice that on December 16, 2004, Iroquois Gas Transmission System, L.P. (Iroquois) tendered for filing as part of its FERC Gas Tariff, First Revised Volume No. 1, Substitute Third Revised Sheet No. 88, to be effective on December 17, 2004.

Iroquois states that copies of its filing were served on all jurisdictional

DEPARTMENT OF ENERGY : Federal Energy Regulatory Commission

16. Portland General Electric Company; Notice of Authorization for Continued Project Operation

NOTICES: Portland General Electric Co.,

December 22, 2004.

The license for Portland General Electric Company's Bull Run Project No. 477, located on the Sandy, Little Sandy, and Bull Run Rivers in Clackamas County, Oregon, was issued for a period ending November 16, 2004. Section 15(a)(1) of the Federal Power Act (FPA), 16 U.S.C. 808(a)(1), requires the Commission, at the expiration

DEPARTMENT OF ENERGY : Federal Energy Regulatory Commission

17. Transcontinental Gas Pipe Line Corporation; Notice of Application

NOTICES: Transcontinental Gas Pipe Line Corp.,

December 22, 2004.

Take notice that on December 14, 2004, Transcontinental Gas Pipe Line Corporation (Transco), P.O. Box 1396, Houston, Texas 77251, filed an application in Docket No. CP0537000 pursuant to section 7(c) of the Natural Gas Act (NGA) and part 157(A) of the Commission's Regulations, for a certificate of public convenience and

DEPARTMENT OF ENERGY : Federal Energy Regulatory Commission

18. Xcel Energy Services, Inc. and Southwest Power Pool, Inc.; Notice of Initiation of Proceeding and Refund Effective

NOTICES: Xcel Energy Services, Inc., et al.,

December 21, 2004.

On December 17, 2004, the Commission issued an order in the above docketed proceeding. The Commission's order institutes a proceeding in Docket No. EL0541000 under section 206 of the Federal Power Act with respect to the justness and reasonableness of the market based rates of Xcel Energy Services, Inc. and Southwest Power

DEPARTMENT OF ENERGY : Federal Energy Regulatory Commission

19. Northern States Power Company; Notice of Availability of Environmental Assessment

NOTICES: Northern States Power Co.,

December 21, 2004.

In accordance with the National Environmental Policy Act of 1969, as amended, and Federal Energy Regulatory Commission (18 CFR part 380), Commission staff have reviewed the license applications for the Menomonie and Cedar Falls projects (FERC Project Nos. 2181 and 2697) and have prepared an environmental assessment (EA). The

DEPARTMENT OF ENERGY : Federal Energy Regulatory Commission

20. Public Utility District No. 2 of Grant County; Notice of Availability of Final Environmental Assessment

NOTICES: Public Utility District No. 2 of Grant County, WA,

December 21, 2004.

In accordance with the National Environmental Policy Act of 1969 and the Federal Energy Regulatory Commission's (Commission) regulations, 18 CFR part 380 (Order No. 486, 52 FR 47897), the Office of Energy Projects has reviewed the application for implementation of an Interim Protection Plan (IPP) for steelhead and chinook

DEPARTMENT OF ENERGY : Federal Energy Regulatory Commission

21. Assessing the State of Wind Energy in Wholesale Electricity Markets; Notice Requesting Post-Technical Conference

NOTICES: Wind energy in wholesale electricity markets; technical conference report,

December 21, 2004.On December 1, 2004, the Federal Energy Regulatory Commission (Commission or FERC) held a technical conference in the above referenced docket to assess the state of wind energy in wholesale electricity markets. Specifically, the conference focused on potential policy changes that would better accommodate the participation of wind
DEPARTMENT OF ENERGY : Federal Energy Regulatory Commission

22. BS Energy LP; Notice of Issuance of Order

NOTICES: BS Energy LP,

December 23, 2004.

BS Energy LP (BSELP) filed an application for marketbased rate authority, with an accompanying tariff. The proposed rate tariff provides for wholesale sales of energy and capacity at marketbased rates. BSELP also requested waiver of various Commission regulations. In particular, BSELP requested that the Commission grant

DEPARTMENT OF ENERGY : Federal Energy Regulatory Commission

23. Destin Pipeline Company, L.L.C.; Notice of Proposed Changes in FERC Gas Tariff

NOTICES: Destin Pipeline Co., L.L.C.,

December 21, 2004.

Take notice that on December 15, 2004, Destin Pipeline Company, L.L.C. (Destin) tendered for filing as part of its FERC Gas Tariff, Original Volume No. 1, the tariff sheets listed on Appendix A to the filing, to become effective January 14, 2005.

Destin states that this filing, made in accordance with the provisions of

DEPARTMENT OF ENERGY : Federal Energy Regulatory Commission

24. Duke Power, a Division of Duke Power Corporation; Notice of Initiation of Proceeding and Refund Effective Date

NOTICES: Duke Power,

December 21, 2004.

On December 15, 2004, the Commission issued an order in the above docketed proceeding. The Commission's order institutes a proceeding in Docket No. EL054000 under section 206 of the Federal Power Act with respect to the justness and reasonableness of Duke Power's marketbased rates.

The refund effective date in Docket No.

DEPARTMENT OF ENERGY : Federal Energy Regulatory Commission

25. Duke Power, a Division of Duke Power Corporation; Notice of Initiation of Proceeding and Refund Effective Date

NOTICES: Duke Power,

December 21, 2004.

On December 15, 2004, the Commission issued an order in the above docketed proceeding. The Commission's order institutes a proceeding in Docket No. EL054000 under section 206 of the Federal Power Act with respect to the justness and reasonableness of Duke Power's marketbased rates.

The refund effective date in Docket No.