NOTICES: Destin Pipeline Company, L.L.C.,
Published: 2004-12-28
December 20, 2004.
Take notice that on December 15, 2004, Destin Pipeline Company,
L.L.C. (Destin) tendered for filing as part of its FERC Gas Tariff,
Original Volume No. 1, the tariff sheets listed on Appendix A to the filing, to become effective January 14, 2005.
Destin states that this filing, made in accordance with the
provisions of
NOTICES: Enbridge Pipelines (KPC),
Published: 2004-12-28
December 21, 2004.
Take notice that on December 13, 2004, Enbridge Pipelines (KPC),
formerly Kansas Pipeline Company (KPC), (Enbridge KPC) submitted a
refund plan pursuant to Enbridge Pipelines (KPC), 109 FERC ] 61,042 (2004) (October 8 Order), issued in Docket No. CP96152030.
Enbridge KPC states that the refund plan describes the
NOTICES: Southern Star Central Gas Pipeline, Inc.,
Published: 2004-12-28
December 21, 2004.
Take notice that on December 15, 2004, Southern Star Central Gas
Pipeline, Inc. (Southern Star), formerly Williams Gas Pipelines
Central, Inc., submitted a compliance filing pursuant to Commission
order issued September 10, 1997, in Docket Nos. RP97369000, et al.,
regarding collection of Kansas ad valorem taxes and the
NOTICES: Environmental Management Site-Specific Advisory Board—; Fernald Site, OH,
Published: 2004-12-28
This notice announces a meeting of the Environmental
Management SiteSpecific Advisory Board (EMSSAB), Fernald. The Federal
Advisory Committee Act (Public Law No. 92463, 86 Stat. 770) requires
that public notice of this meeting be announced in the Federal
Register.
NOTICES: High Energy Physics Advisory Panel,
Published: 2004-12-28
This notice announces a meeting of the High Energy Physics
Advisory Panel (HEPAP). Federal Advisory Committee Act (Public Law 92
463, 86 Stat. 770) requires that public notice of these meetings be
announced in the Federal Register.
NOTICES: Alaska, et al.,
Published: 2004-12-27
December 17, 2004.
Take notice that on December 15, 2004, the State of Alaska (Alaska)
tendered for filing a Complaint against Exxon Mobil Pipeline Co; Conoco
Phillips Transportation Alaska, Inc; Phillip Transportation Alaska;
Unocal Pipeline Co.; and Koch Alaska Pipeline Co. (collectively, TAPS Carriers).
Alaska files this complaint pursuant
NOTICES: Anadarko Petroleum Corp., et al.,
Published: 2004-12-27
December 17, 2004.
Take notice that on December 16, 2004, Anadarko Petroleum
Corporation (Anadarko), tendered for filing a Complaint against BP
Pipelines (Alaska) Inc.; ConocoPhillips Transportation Alaska, Inc.;
ExxonMobile Pipeline Company; Koch Alaska Pipeline Company LLC; and
Unocal Pipeline Company (TAPS Carriers). Anadarko alleges that the
NOTICES: ISO New England Inc., et al.,
Published: 2004-12-27
December 17, 2004.
Take notice that on December 10, 2004, ISO New England Inc., (ISO)
and the New England transmission owners New England transmission owners
consist of Bangor HydroElectric Company; Central Maine Power Company;
New England Power Company; Northeast Utilities Service Company on
behalf of its operating companies: The Connecticut Light
NOTICES: Vista del Sol LNG Terminal LP et al.,
Published: 2004-12-27
December 17, 2004.
The staff of the Federal Energy Regulatory Commission has prepared
this draft Environmental Impact Statement (EIS) on the liquefied
natural gas (LNG) import terminal and natural gas pipeline facilities
proposed by Vista del Sol LNG Terminal LP and Vista del Sol Pipeline LP
(collectively referred to as Vista del Sol ) in the
NOTICES: Hydroelectric applications,
Published: 2004-12-27
December 17, 2004.
Take notice that the following hydroelectric application has been
filed with the Commission and is available for public inspection:
a. Type of Application: Preliminary permit.
b. Project No.: 12510000.
c. Date filed: June 1, 2004.
d. Applicant: Woodruff Narrows, LLC.
e. Name of Project: Woodruff Narrows Dam
NOTICES: Hydroelectric applications,
Published: 2004-12-27
December 17, 2004.
Take notice that the following hydroelectric application has been
filed with the Commission and is available for public inspection:
a. Type of Application: Preliminary permit.
b. Project No.: 12515000.
c. Date Filed: July 1, 2004.
d. Applicant: Corbett Diversion Hydro, LLC.
e. Name of Project: Corbett
NOTICES: Hydroelectric applications,
Published: 2004-12-27
December 17, 2004.
Take notice that the following hydroelectric application has been
filed with the Commission and is available for public inspection:
a. Type of Application: Preliminary permit.
b. Project No.: 12518000.
c. Date Filed: July 1, 2004.
d. Applicant: Thief Valley Dam Hydro, LLC.
e. Name of Project: Thief Valley Dam
NOTICES: Hydroelectric applications,
Published: 2004-12-27
December 17, 2004.
Take notice that the following hydroelectric application has been
filed with the Commission and is available for public inspection:
a. Type of Application: Preliminary permit.
b. Project No.: 12534000.
c. Date Filed: September 1, 2004.
d. Applicant: Pacific Energy Resources, LLC.
e. Name of Project: Wailua
NOTICES: Hydroelectric applications,
Published: 2004-12-27
December 17, 2004.
Take notice that the following hydroelectric application has been
filed with the Commission and is available for public inspection:
a. Type of Application: Preliminary permit.
b. Project No.: 12535000.
c. Date Filed: September 1, 2004.
d. Applicant: Easton Diversion Dam Hydro, LLC.
e. Name of Project: Easton
NOTICES: Hydroelectric applications,
Published: 2004-12-27
December 17, 2004.
Take notice that the following hydroelectric application has been
filed with the Commission and is available for public inspection:
a. Type of Application: Preliminary Permit.
b. Project No.: 12538000.
c. Date filed: September 10, 2004.
d. Applicant: Oologah Lake Dam Hydro, LLC.
e. Name of Project: Oologah
NOTICES: Hydroelectric applications,
Published: 2004-12-27
December 17, 2004.
Take notice that the following hydroelectric application has been
filed with the Commission and is available for public inspection.
a. Type of Application: New major license.
b. Project No.: P2146; P82; P618.
c. Applicant: Alabama Power Company.
d. Name of Project: Coosa River Hydroelectric Project (P2146)
which
NOTICES: Hydroelectric applications,
Published: 2004-12-27
December 17, 2004.
Take notice that the following hydroelectric application has been
filed with the Commission and is available for public inspection.
a. Type of Application: New major license.
b. Project No.: P2165015.
c. Applicant: Alabama Power Company.
d. Name of Project: Warrior River Hydroelectric Project, which
includes the
NOTICES: ISO New England Inc., et al.,
Published: 2004-12-27
December 17, 2004.
Take notice that on December 10, 2004, the New England Power Pool
(NEPOOL), through the NEPOOL Participants Committee, ISO New England
Inc. (ISONE) and the New England transmission owners (collectively,
the Settling Parties) submitted a compliance filing to explain how a
review board process will operate under the regional
NOTICES: New York Independent System Operator, Inc.,
Published: 2004-12-23
December 15, 2004.
Take notice that on December 1, 2004, the New York Independent
System Operator, Inc. (NYISO) submitted a sixth semiannual report on
the status of its demand side management programs, and the addition of
new generation resources in New York State in compliance with the Commission's previous orders in Docket No. ER013001000.
NOTICES: Northern Border Pipeline Co.,
Published: 2004-12-23
December 15, 2004.
Take notice that on December 7, 2004, Northern Border Pipeline
Company (Northern Border) tendered for filing to become part of
Northern Border's FERC Gas Tariff, First Revised Volume No. 1, Fifth
Revised Sheet No. 99A, to become effective November 1, 2004. [[Page 76934]]
Northern Border states that the purpose of this
NOTICES: TransCanada Hydro Northeast, Inc.,
Published: 2004-12-23
December 15, 2004.
Take notice that on December 13, 2004, TransCanada Hydro Northeast
Inc. (TC Hydro NE) submitted an amendment to its October 29, 2004
application requesting that the Commission accept for filing a market
based tariff for TC Hydro NE, and otherwise grant applicant the
authority to sell energy and capacity and ancillary services
NOTICES: Williston Basin Interstate Pipeline Co.,
Published: 2004-12-23
December 16, 2004.
Take notice that on December 3, 2004, Williston Basin Interstate
Pipeline Company (Williston Basin) tendered for filing as part of its
FERC Gas Tariff, Second Revised Volume No. 1, Second Revised Volume No.
1, Eleventh Revised Sheet No. 376, to become effective December 3, 2004.
Williston Basin has revised the
NOTICES: Hopkins Ridge Wind Interconnection Project, WA,
Published: 2004-12-23
This notice announces the availability of the ROD to
interconnect the proposed Hopkins Ridge Wind Energy Project into the
Federal Columbia River Transmission System, as requested by RES America
Developments. Transmission services would be provided for 150 megawatts
of the output of the proposed wind project. This decision is consistent
with and
NOTICES: Kiowa Power Partners, LLC, et al.,
Published: 2004-12-23
December 15, 2004.
Take notice that on December 14, 2004, Kiowa Power Partners, LLC
(Kiowa) filed a Complaint with the Commission, pursuant to section 206
of the Federal Power Act, against Public Service Company of Oklahoma
and American Electric Power Service Corporation (collectively, PSO).
The Complaint asserts that PSO is violating the
NOTICES: Tenaska Gateway Partners, Ltd., et al.,
Published: 2004-12-23
December 15, 2004.
Take notice that on December 14, 2004, Tenaska Gateway Partners,
Ltd. (Tenaska Gateway) filed a Complaint with the Commission, pursuant
to section 206 of the Federal Power Act, against Southwestern Electric
Power Company and American Electric Power Service Corporation
(collectively, SWEPCO). The Complaint asserts that SWEPCO