NOTICES: Eastland Power LLC,
Published: 2008-05-05
April 25, 2008.
Eastland Power LLC (Eastland Power) filed an application for
marketbased rate authority, with an accompanying rate schedule. The
proposed marketbased rate schedule provides for the sale of energy and
capacity. Eastland Power also requested waivers of various Commission
regulations. In particular, Eastland Power requested that
NOTICES: Combined Notice of Filings,
Published: 2008-05-02
April 25, 2008.
Take notice that the Commission received the following electric corporate filings:
Docket Numbers: EC0859000.
Applicants: Harbinger Capital Partners Master Fund I; Harbinger Capital Partners Special Situation.
Description: Supplement to Section 203 Application of Harbinger
Capital Partners Master Fund I, Ltd., et al.
NOTICES: Worsham-Steed Gas Storage, L.P,
Published: 2008-05-02
April 25, 2008.
Take notice that on April 17, 2008, WorshamSteed Gas Storage, L.P.
filed a Statement of Operating Conditions in compliance with section
284.123(e) of the Commission's Regulations and Ordering Paragraph (C)
of the Commission's letter order issued on May 11, 2007, in Docket No. PR076000.
Any person desiring to participate in
NOTICES: AES Sparrows Point LNG, LLC, et al.,
Published: 2008-05-02
April 25, 2008.
The staff of the Federal Energy Regulatory Commission (FERC or
Commission) in cooperation with the U.S. Army Corps of Engineers (COE),
the U.S. Coast Guard, (Coast Guard), and the U.S. Environmental
Protection Agency (EPA) has prepared a draft Environmental Impact
Statement (EIS) for a liquefied natural gas (LNG) import terminal
NOTICES: Biomass Research and Development Technical Advisory Committee,
Published: 2008-05-02
This notice announces an open meeting of the Biomass Research
and Development Technical Advisory Committee under the Biomass Research
and Development Act of 2000. The Federal Advisory Committee Act (Pub.
L. No. 92463, as amended) requires that agencies publish these notices
in the Federal Register to allow for public participation. This notice
NOTICES: 2012 Tiered Rate Methodology Proceeding,
Published: 2008-05-01
BPA is proposing to adopt a new tiered rate design for setting
its Priority Firm Power (PF) rates beginning with the FY 20122013 rate
period. The primary feature of this Tiered Rate Methodology (TRM)
proposal is one rate tier (Tier 1) based on generation output and costs
attributed to BPA's current Federal base system resources and a second
rate
RULES: Annual Update of Filing Fees,
Published: 2008-05-01
In accordance with 18 CFR 381.104, the Commission issues this
update of its filing fees. This notice provides the yearly update using
data in the Commission's Management, Administrative, and Payroll System
to calculate the new fees. The purpose of updating is to adjust the
fees on the basis of the Commission's costs for Fiscal Year 2007.
NOTICES: Combined Notice of Filings,
Published: 2008-05-01
April 23, 2008.
Take notice that the Commission has received the following Natural Gas Pipeline Rate and Refund Report filings:
Docket Numbers: RP96272074.
Applicants: Northern Natural Gas Company.
Description: Northern Natural Gas Company submits 50 Revised Sheet
66A et al. of its FERC Gas Tariff, Fifth Revised Volume 1 effective
NOTICES: Combined Notice of Filings,
Published: 2008-05-01
April 25, 2008.
Take notice that the Commission has received the following Natural Gas Pipeline Rate and Refund Report filings:
Docket Numbers: RP96383085.
Applicants: Dominion Transmission, Inc.
Description: Dominion Transmission, Inc. submits Tenth Revised Sheet 1405 effective April 18, 2008.
Filed Date: 04/17/2008.
NOTICES: Combined Notice of Filings,
Published: 2008-05-01
April 22, 2008.
Take notice that the Commission received the following electric corporate filings:
Docket Numbers: EC0867000.
Applicants: LS Power Development, LLC; Luminus Management, LLC.
Description: LS Power Development, LLC and Luminus Management, LLC
submit a supplement to their joint application submitted 4/8/08.
Filed
NOTICES: Pepco Energy Services, Inc., et al.,
Published: 2008-04-30
April 23, 2008.
Take notice that on April 22, 2008, Pepco Energy Services, Inc.
(PES) filed a formal complaint against PJM Interconnection, L.L.C.
(PJM) pursuant to section 206 of the Federal Power Act, and Rule 206 of
the Federal Energy Regulatory Commission's Rules of Practice and
Procedure, 18 CFR 385.206, alleging that provisions of PJM's
NOTICES: PJM Interconnection, L.L.C.,
Published: 2008-04-30
April 23, 2008.
Take notice that on April 15, 2008, PJM Interconnection, L.L.C.
filed a Petition for Declaratory Order requesting the Commission to
resolve uncertainty regarding the processing of currently pending
interconnection requests and resulting cost allocation determinations
arising from reversals of previously announced retirements,
NOTICES: Virginia Electric and Power Company,
Published: 2008-04-30
April 23, 2008.
Take notice that on April 22, 2008, Virginia Electric and Power Company filed a material amendment to its March
[[Page 23456]]
10, 2008, Application to Terminate Purchase Obligation. The amendment
is titled a motion for leave to file answer and answer to Smurfit Stone
Container Corporation's motion to intervene, limited protest
NOTICES: Meetings; Sunshine Act,
Published: 2008-04-30
April 25, 2008.
The following notice of meeting is published pursuant to Section
3(a) of the Government in the Sunshine Act (Pub. L. No. 94409), 5 U.S.C. 552b:
Agency Holding Meeting: Federal Energy Regulatory Commission. Date and Time: May 2, 2008, 9:30 a.m.
Place: Room 2C, Commission Meeting Room, 888 First Street, NE.,
Washington, DC 20426.
NOTICES: Agency Information Collection Activities; Proposals, Submissions, and Approvals,
Published: 2008-04-30
The Department of Energy (DOE) has submitted an information
collection package to OMB for review under the provisions of the
Paperwork Reduction Act of 1995. The package requests approval of the
information collection described in this notice. Comments are invited
on: (a) Whether the proposed collection of information is necessary for
the proper
NOTICES: Stingray Pipeline Company, LLC,
Published: 2008-04-30
April 23, 2008.
Take notice that on April 14, 2008, Stingray Pipeline Company,
L.L.C. (Stingray), 1100 Louisiana, Suite 3300, Houston, Texas 77002,
filed in Docket No. CP08151000, an application under section 7 of the
Natural Gas Act (NGA) and Part 157 of the Federal Energy Regulatory
Commission's (Commission) regulations for a certificate of
PROPOSED RULES: Electronic Tariff Filings,
Published: 2008-04-29
The Federal Energy Regulatory Commission is proposing to
revise its previous Notice of Proposed Rulemaking for electronic tariff
filing. The revised proposal would require that all tariffs and tariff
revisions and rate change applications for the public utility, natural
gas pipeline, and oil pipeline industries be filed electronically
according to
NOTICES: Upper Peninsula Power Company & WI,
Published: 2008-04-29
April 22, 2008.
In accordance with the National Environmental Policy Act of 1969
and the Federal Energy Regulatory Commission's regulations, 18 CFR Part
380 (Order No. 486, 52 FR 47879), the Office of Energy Projects has
reviewed the proposed lake level amendment for the bond Falls Project,
located in the Ontonagon River Basin in Ontonagon and
NOTICES: Combined Notice of Filing,
Published: 2008-04-29
Regional Transmission Organizations; Bangor HydroElectric
Company, et al.; New York Independent System Operator, Inc., et al.;
PJM Interconnection, L.L.C., et al.; PJM Interconnection, L.L.C.; ISO
New England, Inc.; New York Independent System Operator, Inc.; Notice of Filing
April 21, 2008.
Take notice that PJM Interconnection, L.L.C., New
NOTICES: New Brunswick Power Transmission Corp.,
Published: 2008-04-29
April 21, 2008.
Take notice that on April 18, 2008, New Brunswick Power
Transmission Corporation, New Brunswick System Operator, and Northern
Maine Independent System Administrator, Inc. (collectively,
Complainants), pursuant to sections 206 and 306 of the Federal Power
Act, 16 U.S.C. 824e, 825e, and Rule 206 of Practice and Procedures of
the
NOTICES: Composition of Proxy Groups for Determining Gas and Oil Pipeline Return on Equity,
Published: 2008-04-29
Issued April 17, 2008.
Before Commissioners: Joseph T. Kelliher, Chairman; Suedeen G.
Kelly, Marc Spitzer, Philip D. Moeller, and Jon Wellinghoff.
1. On July 19, 2007, the Commission issued a proposed policy
statement concerning the composition of the proxy groups used to
determine gas and oil pipelines' return on equity (ROE) under the
NOTICES: Western Greenbrier Co-Production Demonstration Project, Rainelle, Greenbrier County, WV,
Published: 2008-04-29
DOE has decided to implement the Proposed Action alternative,
identified as the preferred alternative, in the Western Greenbrier Co
Production Demonstration Project, Final Environmental Impact Statement
(DOE/EIS0361; November 2007) (FEIS). That alternative is to provide
approximately $107.5 million (up to 50% of the development costs) to
Western
NOTICES: Parker-Davis Project; WAPA-138 Rate Order No.,
Published: 2008-04-29
The Western Area Power Administration (Western) is proposing
modifications to the rate methodology used to develop ParkerDavis
Project (PDP) firm electric and transmission service formula rates.
The modifications to the rate methodology will change the allocation
factors used to apportion certain expenses between generation and
transmission
NOTICES: Gibson Dam Hydroelectric Project, LLC,
Published: 2008-04-29
April 21, 2008.
Take notice that the following hydroelectric application has been
filed with the Commission and is available for public inspection.
a. Type of Application: Major ProjectExisting Dam.
b. Project No.: 12478002.
c. Date Filed: April 14, 2008.
d. Applicant: Gibson Dam Hydroelectric Project, LLC.
e. Name of Project:
NOTICES: Colorado Hub Connection Project,
Published: 2008-04-29
April 21, 2008.
The staff of the Federal Energy Regulatory Commission (FERC or
Commission) will prepare an environmental assessment (EA) that will
discuss the potential environmental impacts of the planned Colorado Hub
Connection Project (CHC). This project would involve the construction
and operation of about 29 miles of natural gas pipeline