SUBJECT CATEGORY: Loveland Area Projects--Rate Order No. WAPA-141
DOCUMENT SUMMARY: This action is being taken to extend the existing Loveland Area Projects (LAP) transmission and ancillary services formula rates through February 28, 2011. The existing LAP transmission and ancillary services formula rates will expire February 28, 2009, with the exception of the Regulation and Frequency Response service rate which expires May 31, 2011.
SUMMARY: Loveland Area Projects,
The existing formula rates approved under Rate Order No. WAPA106
\1\ became effective on March 1, 2004, and are approved through
February 28, 2009. Subsequently, Rate Schedule LAS3, Regulation and
Frequency Response, was revised and approved under Rate Order No. WAPA
118 and became effective June 1, 2006, and is approved through May 31,
2011.\2\ Western is proposing to extend the existing LAP transmission
and ancillary services formula rates pursuant to 10 CFR part 903.23
(b). The existing LAP rate formula methodology collects annual revenue
sufficient to recover annual expenses, including interest and capital
requirements, thus ensuring repayment of the project within the cost
recovery criteria set forth in DOE order RA 6120.2. Western is seeking
this extension to provide more time for the evaluation of new rate
requirements for transmission and ancillary services mandated under
FERC Order 890 and the evaluation of adjustments to the formulae for
ancillary services. For these reasons, Western is extending the
existing rate formulae for transmission and ancillary services through February 28, 2011.
\1\ WAPA106 was approved by FERC on a final basis on January 31, 2005, in Docket No. EF045182000 (110 FERC ] 62,084).
\2\ WAPA118 was approved by FERC on a final basis on November 17, 2006, in Docket No. EF065182000 (117 FERC ] 62,163).
Western did not have a consultation and comment period and did not
hold public information and comment forums, in accordance with 10 CFR
part 903.23(b). Following review of Western's proposal with the DOE, I
hereby approve Rate Order No. WAPA141 which extends the existing LAP transmission and ancillary services rate
[[Page 48383]]
schedules LNT1, LFPT1, LNFPT1, LAS1, LAS2, LAS4, LAS5, LAS6 and LAS7 through February 28, 2011.
Dated: August 12, 2008.
Jeff Kupfer,
Acting Deputy Secretary.
Department of Energy
Deputy Secretary
Rate Order No. WAPA141.
In the Matter of: Western Area Power Administration Rate
Extension for Loveland Area Projects Transmission and Ancillary Services Formula Rates.
Order Confirming and Approving an Extension of the Loveland Area Projects Transmission and Ancillary Services Formula Rates
The Loveland Area Projects (LAP) transmission and ancillary services rate formulae were established following section 302(a) of the Department of Energy (DOE) Organization Act (42 U.S.C. 7152). This act transferred to and vested in the Secretary of Energy the power marketing functions of the Secretary of the Department of the Interior and the Bureau of Reclamation under the Reclamation Act of 1902 (ch. 1093, 32 Stat. 388), as amended and supplemented by subsequent laws, particularly section 9(c) of the Reclamation Project Act of 1939 (43 U.S.C. 485h(c)), and other Acts that specifically apply to the project system involved.
By Delegation Order No. 00037.00 effective December 6, 2001, the Secretary of Energy delegated: (1) The authority to develop power and transmission rates to the Administrator of the Western Area Power Administration (Western); (2) the authority to confirm, approve, and place such rates into effect on an interim basis to the Deputy Secretary of Energy; and (3) the authority to confirm, approve, and place into effect on a final basis, to remand, or to disapprove such rates to the Federal Energy Regulatory Commission (FERC). This rate extension is issued pursuant to the Delegation Order and the DOE rate extension procedures at 10 CFR part 903.23(b).
The existing formula rates, approved under Rate Order No. WAPA 106, were approved for five (5) years and are effective through February 28, 2009. Subsequently, Rate Schedule LAS3, Regulation and Frequency Response, was revised and approved for five (5) years under Rate Order No. WAPA118 and is effective through May 31, 2011. Western is not seeking to extend Rate Schedule LAS3 for Regulation and Frequency Response service as part of this extension.
On February 28, 2009, Western's LAP transmission and ancillary services formula rates will expire, with the exception of Regulation and Frequency Response service, which will expire May 31, 2011. Western is proposing to extend the existing LAP transmission and ancillary services formula rates pursuant to 10 CFR part 903.23(b). The existing LAP rate formulae methodologies collect annual revenue sufficient to recover annual expenses (including interest) and capital requirements, thus ensuring repayment of the project within the cost recovery criteria set forth in DOE order RA 6120.2. Western is seeking this extension to provide more time for the evaluation of new rate requirements for transmission and ancillary services mandated under FERC Order 890 and the evaluation of adjustments to the formulae for ancillary services. For these reasons, Western is extending the existing rate formulae for transmission and ancillary services through February 28, 2011.
The process will take several months to complete because of the complex issues Western and its interested parties must address. It will also offer opportunities for public information and comment forums. For these reasons, Western seeks to extend existing Rate Schedules LNT1, LFPT1, LNFPT1, LAS1, LAS2, LAS4, LAS5, LAS6 and LAS7. Western did not have a consultation and comment period and did not hold public information and comment forums, in accordance with 10 CFR part 903.23(b).
In view of the above and under the authority delegated to me, I
hereby extend for a period effective from March 1, 2009, through
February 28, 2011, the existing rate schedules LNT1, LFPT1, L NFPT1, LAS1, LAS2, LAS4, LAS5, LAS6 and LAS7 for LAP
transmission and ancillary services, excluding LAS3 for Regulation and Frequency Response service.
Dated: August 12, 2008.
Jeff Kupfer,
Acting Deputy Secretary.
[FR Doc. E819161 Filed 81808; 8:45 am]
BILLING CODE 645001P
FOR FURTHER INFORMATION CONTACT Mr. James D. Keselburg, Regional
Manager, Rocky Mountain Region, Western Area Power Administration, P.O. Box 3700, Loveland, CO 805393003, (970) 4617201, email
keselbrg@wapa.gov, or Ms. Sheila Cook, Rates Manager, Rocky Mountain
Region, Western Area Power Administration, P.O. Box 3700, Loveland, CO
805393003, (970) 4617211, email scook@wapa.gov.
14 CFR Part 39 40 CFR Part 52 14 CFR Part 71 33 CFR Part 165 50 CFR Part 679 47 CFR Part 73 26 CFR Part 1 40 CFR Part 180 33 CFR Part 117 50 CFR Part 17 44 CFR Part 67 50 CFR Part 648 14 CFR Part 97 33 CFR Part 100 40 CFR Part 63 50 CFR Part 622 44 CFR Part 65 50 CFR Part 660 26 CFR Part 301 39 CFR Part 111 40 CFR Part 300 6 CFR Part 5 40 CFR Part 271 47 CFR Part 64 40 CFR Parts 52 and 81 50 CFR Part 665 44 CFR Part 64 10 CFR Part 50 49 CFR Part 571 47 CFR Part 76