Browse: Departments Dates Agencies
Docket ID: [Docket Nos. CP06-61-000; CP01-23-003]
SUBJECT CATEGORY: North Baja Pipeline, LLC; Notice of Motion To Vacate Certificate in Part
DOCUMENT SUMMARY: August 20, 2008.
Take notice that on June 25, 2008, North Baja Pipeline, LLC (North Baja), 1400 SW Fifth Avenue, Suite 900, Portland, Oregon 94201, filed in Docket Nos. CP0661000 and CP0123003, a motion to vacate a portion of the certificate authority granted on October 2, 2007, in those dockets, allowing North Baja to modify and expand its existing pipeline system to facilitate the importation of regasified liquefied natural gas from Mexico into California and Arizona (Expansion Project). North Baja states that the planned construction of a 45.7 mile, 16inch diameter lateral pipeline extending from a point north of its Ogilby Meter Station to the Imperial Irrigation District's El Centro Generating Facility in Imperial County, California (the ``IID Lateral'' proposed as construction Phase IA), is no longer necessary due to the Imperial Irrigation District's decision to terminate its precedent agreement. North Baja seeks to vacate the portion of its certificate that authorizes the IID Lateral facilities, proposed as Phase IA of the project.
The motion is on file with the Commission and open for public inspection. This motion is available for review at the Commission in the Public Reference Room or may be viewed on the Commission's Web site at http://www.ferc.gov using the ``eLibrary'' link. Enter the docket number excluding the last three digits in the docket number field to access the document. For assistance, please contact FERC Online Support at FERCOnlineSupport@ferc.gov or toll free at (866) 2083676, or for TTY, contact (202) 5028659.
Any questions regarding the application should be directed to Carl M. Fink, Associate General Counsel, North Baja Pipeline, LLC (North Baja), 1400 SW Fifth Avenue, Suite 900, Portland, Oregon 94201, (503) 8334256.
There are two ways to become involved in the Commission's review of North Baja's request. First, any person wishing to obtain legal status by becoming a party to this proceeding should, on or before the comment date listed below, file with the Federal Energy Regulatory Commission, 888 First Street, NE., Washington, DC 20426, a motion to intervene in accordance with the requirements of the Commission's Rules of Practice and Procedure (18 CFR 385.214 or 385.211) and the Regulations under the NGA (18 CFR 157.10). A person obtaining party status will be placed on the service list maintained by the Secretary of the Commission and will receive copies of all documents filed by the applicant and by all other parties. A party must submit 14 copies of this filing and all subsequent filings made with the Commission and must mail a copy of all filing to the applicant and to every other party in the proceeding. Only parties to the proceeding can ask for court review of Commission orders in the proceeding.
However, other persons do not have to intervene in order to have comments considered. The second way to participate is by filing with the Secretary of the Commission, as soon as possible, an original and two copies of comments in support of or in opposition to North Baja's request. The Commission will consider these comments in determining the appropriate action to be taken, but the filing of a comment alone will not serve to make the filer a party to the proceeding. The Commission's rules require that persons filing comments in opposition to this project provide copies of their protests only to the party or parties directly involved in the protest.
Persons who wish to comment only in support of or in opposition to North Baja's request should submit an original and two copies of their comments to the Secretary of the Commission. The Commission's rules require that persons filing comments in opposition to the project provide copies of their protests only to the applicant. However, the nonparty commenters will not receive copies of all documents filed by other parties or issued by the Commission and will not have the right to seek court review of the Commission's final order.
The Commission strongly encourages electronic filings of comments, protests, and interventions via the internet in lieu of paper. See 18 CFR 385.2001(a)(1)(iii) and the instructions on the Commission's Web site (http://www.ferc.gov) under the ``eFiling'' link.
Comment Date: September 10, 2008.
Kimberly D. Bose,
Secretary.
[FR Doc. E819814 Filed 82608; 8:45 am]
BILLING CODE 671701P
SUMMARY: North Baja Pipeline, LLC,
DOCUMENT BODY 2: August 20, 2008.
Take notice that on June 25, 2008, North Baja Pipeline, LLC (North Baja), 1400 SW Fifth Avenue, Suite 900, Portland, Oregon 94201, filed in Docket Nos. CP0661000 and CP0123003, a motion to vacate a portion of the certificate authority granted on October 2, 2007, in those dockets, allowing North Baja to modify and expand its existing pipeline system to facilitate the importation of regasified liquefied natural gas from Mexico into California and Arizona (Expansion Project). North Baja states that the planned construction of a 45.7 mile, 16inch diameter lateral pipeline extending from a point north of its Ogilby Meter Station to the Imperial Irrigation District's El Centro Generating Facility in Imperial County, California (the ``IID Lateral'' proposed as construction Phase IA), is no longer necessary due to the Imperial Irrigation District's decision to terminate its precedent agreement. North Baja seeks to vacate the portion of its certificate that authorizes the IID Lateral facilities, proposed as Phase IA of the project.
The motion is on file with the Commission and open for public inspection. This motion is available for review at the Commission in the Public Reference Room or may be viewed on the Commission's Web site at http://www.ferc.gov using the ``eLibrary'' link. Enter the docket number excluding the last three digits in the docket number field to access the document. For assistance, please contact FERC Online Support at FERCOnlineSupport@ferc.gov or toll free at (866) 2083676, or for TTY, contact (202) 5028659.
Any questions regarding the application should be directed to Carl M. Fink, Associate General Counsel, North Baja Pipeline, LLC (North Baja), 1400 SW Fifth Avenue, Suite 900, Portland, Oregon 94201, (503) 8334256.
There are two ways to become involved in the Commission's review of North Baja's request. First, any person wishing to obtain legal status by becoming a party to this proceeding should, on or before the comment date listed below, file with the Federal Energy Regulatory Commission, 888 First Street, NE., Washington, DC 20426, a motion to intervene in accordance with the requirements of the Commission's Rules of Practice and Procedure (18 CFR 385.214 or 385.211) and the Regulations under the NGA (18 CFR 157.10). A person obtaining party status will be placed on the service list maintained by the Secretary of the Commission and will receive copies of all documents filed by the applicant and by all other parties. A party must submit 14 copies of this filing and all subsequent filings made with the Commission and must mail a copy of all filing to the applicant and to every other party in the proceeding. Only parties to the proceeding can ask for court review of Commission orders in the proceeding.
However, other persons do not have to intervene in order to have comments considered. The second way to participate is by filing with the Secretary of the Commission, as soon as possible, an original and two copies of comments in support of or in opposition to North Baja's request. The Commission will consider these comments in determining the appropriate action to be taken, but the filing of a comment alone will not serve to make the filer a party to the proceeding. The Commission's rules require that persons filing comments in opposition to this project provide copies of their protests only to the party or parties directly involved in the protest.
Persons who wish to comment only in support of or in opposition to North Baja's request should submit an original and two copies of their comments to the Secretary of the Commission. The Commission's rules require that persons filing comments in opposition to the project provide copies of their protests only to the applicant. However, the nonparty commenters will not receive copies of all documents filed by other parties or issued by the Commission and will not have the right to seek court review of the Commission's final order.
The Commission strongly encourages electronic filings of comments, protests, and interventions via the internet in lieu of paper. See 18 CFR 385.2001(a)(1)(iii) and the instructions on the Commission's Web site (http://www.ferc.gov) under the ``eFiling'' link.
Comment Date: September 10, 2008.
Kimberly D. Bose,
Secretary.
[FR Doc. E819814 Filed 82608; 8:45 am]
BILLING CODE 671701P
14 CFR Part 39 40 CFR Part 52 14 CFR Part 71 33 CFR Part 165 50 CFR Part 679 47 CFR Part 73 26 CFR Part 1 40 CFR Part 180 33 CFR Part 117 50 CFR Part 17 44 CFR Part 67 50 CFR Part 648 14 CFR Part 97 33 CFR Part 100 40 CFR Part 63 50 CFR Part 622 44 CFR Part 65 50 CFR Part 660 26 CFR Part 301 39 CFR Part 111 40 CFR Part 300 6 CFR Part 5 40 CFR Part 271 47 CFR Part 64 40 CFR Parts 52 and 81 50 CFR Part 665 44 CFR Part 64 10 CFR Part 50 49 CFR Part 571 47 CFR Part 76