Docket ID: [Docket No.: 030-10346; License No.: 50-16084-01; EA-08-196]
SUBJECT CATEGORY: In the Matter of Alaska Industrial X-Ray, Inc., Anchorage, AK; Order Modifying License (Effective Immediately)
DOCUMENT SUMMARY: I
Alaska Industrial XRay, Inc. (AIX or Licensee) is the holder of Materials License No. 501608401 issued by the Nuclear Regulatory Commission (NRC or Commission) pursuant to 10 CFR Parts 3036, 39, 40, and 70 and last amended on November 2, 2007, and due to expire on March 31, 2011. The license authorizes AIX to possess and use sealed radioactive sources in conducting industrial radiography activities in accordance with the conditions specified therein.
In June 2007, the NRC conducted an onsite inspection and began an investigation into AIX activities to determine whether deliberate violations of NRC requirements occurred. During the investigation, the NRC discovered that AIX radiographers had conducted radiography activities in violation of 10 CFR 34.41(a) on multiple occasions at the Arctic Slope Regional Corporation Energy Services (ASRC) site and the Golovin site, both temporary jobsites. Of concern is that the NRC previously had issued an identical violation of 10 CFR 34.41(a) involving deliberate misconduct at the ASRC site on April 25, 2001 (EA 01015). Based on the preliminary information from the investigation, the NRC issued an Order Suspending Licensed Activities (EA07261) on October 19, 2007, which, among other conditions, required that AIX suspend its radiography activities until adequate assurance could be provided by independent means that AIX would comply with NRC requirements when conducting licensed activities. On November 8, 2007, the NRC relaxed the Order based on several actions taken and commitments made by AIX to the NRC. The Order was a temporary measure while the NRC completed its investigation and reviewed the results. Once completed, the results of the inspection and investigation were discussed with AIX during a telephonic exit briefing on April 23, 2008, and were documented in NRC Inspection Report No. 03010346/0701 dated May 20, 2008.
On June 5, 2008, a predecisional enforcement conference (PEC) was [[Page 50652]]
conducted with AIX in Anchorage, Alaska, to discuss with the company
and its employees the apparent violations, their significance, their
root causes, and any corrective actions. The individuals of concern
included two fulltime radiographers, a parttime radiographer, and the
former radiation safety officer (RSO) who, at the time of the PEC, was
employed by AIX as a fulltime radiographer. During the PEC, the four
individuals admitted to committing deliberate violations of 10 CFR
34.41(a) at the ASRC site on multiple occasions over a period of
several years. This information was substantively consistent with their
sworn statements provided to the NRC Office of Investigations. Based on
the investigation, the NRC concluded that this violation had occurred
on multiple occasions from about 2004 until the investigation in June 2007.
In addition, during the PEC, the NRC staff discussed with the president of AIX that during his first interview on July 24, 2007, he denied that violations of the twoperson rule had occurred at the ASRC site. Later, on July 25, 2007, when confronted with information that showed that his radiographers had indeed deliberately violated the two person rule at the ASRC site, the company president stated that he suspected violations of the twoperson rule had occurred at the ASRC site, but took no action to investigate his suspicions or discuss this with his personnel. As a result, the NRC has concluded that the AIX president, with careless disregard, provided the NRC with information about the company that was incomplete or inaccurate, in violation of 10 CFR 30.9(a).
During the PEC, the NRC noted that in 2001 it had issued a Severity
Level III violation of 10 CFR 34.41(a) to AIX for deliberate failures
to follow the twoperson rule at the ASRC site.\1\ The fact that a
prior enforcement action had been issued for the same violation at the
same location was a significant concern to the NRC because it raised
questions about the effectiveness of AIX management oversight to
prevent recurrence of violations.\2\ In fact, a few years later in
about 2004, the former AIX RSO, and almost all of AIX's radiographers
and assistant radiographers who worked at the ASRC site, began
deliberately failing to follow the twoperson rule at the ASRC site.
Further, the reason the violations reoccurred in 20042007 were very
similar to the reasons the violations occurred in 2001: The
radiographers felt that oneperson radiography was safe at the ASRC
site, and following the twoperson rule was unnecessary because
radiographic exposures were performed inside a structure that AIX had
built prior to 2001, intended to meet NRC specifications for a permanent radiographic installation.\3\
\1\ On April 25, 2001, the NRC issued a Notice of Violation for
a Severity Level III violation involving a failure to meet the requirements of 10 CFR 34.41(a) (EA01015).
\2\ As part of the corrective actions for the 2001 violation
involving deliberate failures to follow the twoperson rule at the
ASRC site, the AIX company president, its former RSO, and all
radiographers and assistant radiographers signed a memorandum, in
February 2001, acknowledging that the twoperson rule was to be
followed at the ASRC site. A copy of the memorandum was presented to the NRC in March 2001.
\3\ In 20012002, AIX had requested that the NRC approve the
structure it had built at the ASRC site as a permanent radiographic installation. However, the structure required extensive
modifications in order to meet NRC requirements. AIX did not make
the modifications and, as a result, the NRC never approved it. If
the structure had been approved, then AIX would have been authorized
to conduct radiography with only one individual instead of two.
During the PEC, the company president stated that he could understand why AIX personnel failed to follow the twoperson rule and that he (the company president) might have done it himself if he were conducting radiography. One of the reasons for this was the general belief that the structure provided a similar level of protection as a permanent radiographic installation.
The company president stated that he ``probably suspected'' that AIX radiographers were not abiding by the twoperson rule, but that he ``never went [to the ASRC site] and tried to catch anybody at it.'' Thus, NRC representatives also questioned AIX regarding the lack of management oversight from both the former AIX RSO and the company president.
In addition to the deliberate violations of 10 CFR 34.41(a) and the willful violation of 10 CFR 30.9(a), the NRC representatives noted three additional concerns during the June 2008 PEC. First, during a tour of the ASRC site, the day prior to the June 5th conference, the two trailers which formed the sides of the structure were found to be unlocked and open. This was of concern to the NRC staff because of the potential that ASRC personnel (considered members of the public for purposes of the regulations) might access the trailers during radiography and be exposed to radiation or remove some of the trailer contents, which could reduce the level of shielding. In addition, this undermined NRC's confidence in AIX to meet its commitments because in its letter dated November 1, 2007, AIX committed to keep the trailers locked and to control access to the trailers. This commitment was made to the NRC as a consideration for lifting the Order Suspending License dated October 19, 2007. On June 4, 2008, the NRC staff requested that AIX review the issue and provide additional assurance it would meet its commitments to the NRC. Second, the NRC staff was concerned that radiation streaming could occur through the back of the structure because there was an opening in between the two trailers which formed the back of the structure. The staff questioned whether radiation surveys were conducted to establish that the radiation rope boundaries were adequate. This was important because of the possibility that ASRC personnel (considered members of the public) might at times be present behind the structure and could be exposed to radiation areas in excess of NRC limits. And third, the NRC staff noted that although the focus of the June 5th PEC was deliberate violations associated with radiography at the ASRC site, other examples of failures to comply with 10 CFR 34.41(a) were identified at AIX's Golovin site. Although the NRC did not find any deliberate misconduct associated with the 10 CFR 34.41(a) violations at the AIX Golovin site, corrective actions were needed to correct the violations at that site.
AIX's corrective actions presented at the June 5th PEC included: (1) Continuing to contract with an independent contractor to conduct inspections of AIX radiographers, as AIX committed in response to the NRC's Order Suspending Licensed Activities (EA07261) dated October 19, 2007; (2) changing the RSO in November 2007; (3) reducing the number of radiographic exposures at the Golovin site with NRClicensed material; (4) modifying contractual agreements with ASRC to reduce schedule pressures and to ensure compliance with 10 CFR 34.41(a); and (5) instituting a disciplinary policy to terminate any radiographer who did not follow the twoperson rule. The NRC representatives also discussed concerns about whether the independent oversight was as effective as it could or should be.
These corrective actions did not address the NRC's concerns about
AIX's lack of management oversight in AIX's radiography activities
including the failure to ensure that its employees, including the
former AIX RSO, were following NRC requirements, despite the company
president's suspicions that violations were occurring, as well as the
fact that corrective actions for the 2001 enforcement action were not
effective. As a result, the NRC representatives provided AIX with more time to provide
[[Page 50653]]
any additional corrective actions. By letter dated June 9, 2008, AIX
provided additional corrective actions which included: (1) Conducting
monthly safety meetings; (2) a commitment from the company president to
independently and personally review (audit) each crew on a quarterly
basis at a minimum; (3) performing surveys around the ASRC radiation
exposure area, where instantaneous dose rates were found to exceed 20
millirem/hour in several areas, and AIX applying additional dirt
(shielding) to the perimeter of the structure; and (4) locking and
rebolting the doors to the trailers at the ASRC site which AIX uses as
shielding around the area where radiographic exposures are performed.
In summary, based on the information developed during the inspection, the investigation, and the PEC, the NRC has determined that two violations of NRC requirements occurred. These violations are cited in the enclosed Notice of Violation and Proposed Imposition of Civil Penalty (Notice) dated the same day as this Order, and the circumstances surrounding them are described in detail in the subject inspection report and the cover letter accompanying this Order. The violations involve: (1) Performing radiography at a location other than a permanent radiographic installation without the presence of two qualified individuals, in violation of 10 CFR 34.41(a), and (2) failing to provide the NRC with information that was complete and accurate in all material respects, in violation of 10 CFR 30.9(a). The NRC has determined that willfulness was associated with both violations.
In assessing the safety significance of the violations, the NRC notes that, absent deliberate misconduct, performing radiography in violation of the twoperson rule is significant because the use of two qualified persons during radiographic operations not only provides for a high level of assurance that members of the public will be prevented from entering the restricted area during those operations, but also provides additional protection for the radiographers should one of them become incapacitated while the source is unshielded. The second violation, providing the NRC with incomplete or inaccurate information, impacts the NRC's ability to perform its regulatory function. The violations were more significant given the pervasive deliberate misconduct on the part of the AIX radiographers and assistant radiographers, as well as a senior company official, the RSO at the time; and the careless disregard on the part of the president of the company, in providing the NRC with information that was incomplete or inaccurate. Therefore, these violations have been categorized in accordance with the NRC Enforcement Policy at Severity Level II.
The NRC has determined that additional actions \4\ are needed to
provide reasonable assurance that the public health and safety, as well
as the health and safety of AIX employees, will be maintained. The
circumstances in this case raise serious concerns about AIX company
management's ability or desire to ensure licensed activities are
conducted without undue risk to the public's health and safety, and
that commitments made to the NRC are honored. Therefore, the NRC is
issuing an Order to require (1) Continued independent oversight with
additional specific conditions to ensure AIX's radiographers follow NRC
requirements, (2) that the trailers be locked and that AIX maintain
control over the key, (3) that AIX contract with an independent
consultant to evaluate the AIX radiation safety procedures for
effectiveness, and to provide training to AIX radiographers and
assistant radiographers, and (4) that the president of AIX, perform quarterly audits of your radiographers.
\4\ These actions are in addition to, and separate from, the
attached Notice, which imposes a civil penalty at twice the base for
the Severity Level II problem in the total amount of $20,800. As
fully set out in the Notice, the civil penalty was issued to
emphasize the importance of not engaging in deliberate misconduct,
selfidentifying violations, and taking prompt and comprehensive corrective actions.
Based on the above, the NRC has determined that AIX company management, including the company president, have not provided the level of oversight needed for the company to conduct its activities in compliance with NRC requirements and to meet all its commitments to the NRC. Consequently, I lack the requisite reasonable assurance that the Licensee's current operations can be conducted under License No. 50 1608401 in compliance with the Commission's requirements and that the health and safety of the public, including the Licensee's employees, will be protected. Therefore, the public health and safety interest require that License No. 501608401 be modified to require additional actions so as to provide reasonable assurance that the health and safety of the public will be protected. Furthermore, pursuant to 10 CFR 2.202, I find that the significance of the violations described above is such that the public health and safety interest require that this Order be immediately effective.
Accordingly, pursuant to Sections 81, 161b, 161i, 161o, 182, and
186 of the Atomic Energy Act of 1954, as amended, the Commission's
regulations in 10 CFR 2.202, 2.205, 10 CFR parts 20, 34, and 10 CFR
150.20, it is hereby ordered, effective immediately, that License No. 501608401 is modified as follows:
(1) AIX shall continue use of an independent contractor to provide independent oversight of AIX operations.
(a) AIX shall notify the NRC by fax and the contractor documented
in AIX's letter dated November 1, 2007, by phone, fax or email, on a
weekly basis, of the anticipated AIX work schedule for that week. AIX
will immediately notify the contractor daily, by phone, fax and or
email, as requested by the contractor, of any changes to AIX scheduled
activities. AIX must inform the contractor in writing that the provisions of 10 CFR 30.10 apply to the contractor.
(b) The contractor must conduct unannounced audits and observations
of AIX radiography crews during radiographic exposures in a manner and
location where he is undetected by the radiography crew. After
observing the crews, the contractor may announce himself to the crew in
order to complete his audits of the jobsite. The audits must verify
that AIX personnel are conducting all operations in a safe manner and
in compliance with NRC requirements. The contractor must, to the extent
possible, prevent violations from occurring or continuing as he
observes the radiography crews, even in situations where the crew has not detected his presence prior to the violation.
(c) The unannounced audits shall be conducted at least twice a month when work is being performed.
(d) At least 50 percent of the time, on average over a year, the
contractor must conduct unannounced audits during the second half of
work that is scheduled outside of normal business hours. Normal business hours are 8 a.m. to 5 p.m.
(e) The contractor will provide AIX a monthly report of his audit
activities. The information will be provided to NRC Region IV at the
same time the contractor provides the results to AIX. At a minimum, the
information provided shall include: The date and times of the audit;
the hours (time of the day) in which the crew worked; the names of the
radiographers and assistant radiographers involved in the work; [[Page 50654]]
whether the contractor was detected by the crew prior to the contractor
announcing his presence; and whether or not radiographic operations
were performed safely and in compliance with NRC requirements. The
monthly reports will be sent to the Director, Division of Nuclear Materials Safety, U.S. NRC Region IV.
(f) Individuals with whom AIX contracts to meet this requirement,
must be approved in advance. AIX currently contracts with an individual
who has received prior approval and further approval for this
individual is not needed. In order to receive prior approval for
another individual to perform these independent audits, AIX must
provide the NRC with information regarding the individual's
qualifications and information concerning any prior working
relationships the individual has had with AIX. This information should
be sent to the Director, Division of Nuclear Materials Safety, U.S. NRC Region IV.
(2) The trailers that surround the radiographic site at ASRC will
be locked during the conduct of radiography. AIX must maintain control
over the key such that ASRC personnel cannot obtain the key without the AIX company management's approval.
(3) AIX will contract with an independent consultant to evaluate
the effectiveness of its radiation safety and compliance programs.
(a) Within 60 days of the date of this Order, AIX will submit to
the NRC for approval, the name(s) and qualifications of an independent
consultant to review and evaluate AIX's radiation safety program and compliance program;
(b) Within 30 days of NRC approval of the consultant, the
consultant will commence an assessment of AIX's radiation safety program;
(c) The consultant's assessment will review AIX's training program as follows:
(i) Physical observation of each of AIX's radiographers and
assistant radiographers, on multiple occasions, during the conduct of
radiographic operations, verifying their actions ensure radiation
safety and compliance with NRC requirements. At least 25 percent of the
observations will be conducted at the ASRC site. The purpose of the
observation is to evaluate compliance with NRC requirements and to
provide recommendations to AIX management about improving the work
practices of AIX radiographers to comply with NRC requirements. The
consultant should consider providing recommendations to AIX for
complying with NRC requirements during inclement weather (e.g., winter conditions) during radiographic operations.
(ii) Perform independent radiation measurements around AIX's
structure used at the ASRC site, taking into account changes in the
shielding characteristics as material inside the trailers that form the
walls of the structure vary. The purpose of the measurements will be to demonstrate compliance with 10 CFR part 20 limits.
(iii) Evaluate AIX's Operating and Emergency Procedures.
(iv) Evaluate the effectiveness of the current AIX RSO to oversee
the AIX radiation safety program and to ensure compliance with NRC requirements;
(v) Within 30 days following completion of its reviews, the
consultant will provide AIX a report discussing its findings and
recommendations for program improvements. At the same time the
consultant provides its report to AIX, the consultant will send a copy
to the Director, Division of Nuclear Material Safety, U.S. NRC Region IV.
(d) Within 30 days of receiving the consultant's report, AIX will
provide the NRC, in writing, its position on how it will address the
consultant's findings. In its correspondence to the NRC, AIX will
identify which of the consultant's recommendations it will implement
and the time frame in which it will implement the recommendations. For
those recommendations AIX does not accept, AIX will provide the NRC with its justification.
(e) The consultant will provide training to all AIX employees, managers, and officials. The training will include:
(i) A review of the radiation mishaps involving radiography devices or gauges;
(ii) A review of the potential actions that NRC may take against an individual;
(iii) A review of NRC requirements, AIX's license conditions; and
(iv) A review of AIX's Operating and Emergency Procedures.
(4) The president of AIX shall perform quarterly audits of his
radiographers as they conduct radiography. The audits shall include
observations of his crew during radiographic exposures and, to the
extent possible, must include observations such that the crew cannot
detect his presence. At least 25 percent of the observations will be
conducted at the ASRC site during the second half of work that is
scheduled outside of the normal business hours of 8 a.m. to 5 p.m. The
president of AIX must, to the extent possible, prevent violations from
occurring or continuing as he observes the radiography crews, even in
situations where the crew has not detected his presence prior to the
violation. These audits must be separate and apart from any required
audits performed for compliance with 10 CFR 34.43(e). Records shall be
maintained documenting these audits and the results of his observations.
(5) Information that is required to be sent to the NRC in
Conditions 14 above shall be addressed to: Director, Division of
Nuclear Materials Safety, U.S. NRC Region IV; 612 East Lamar Blvd., Suite 400, Arlington, TX 76011.
The Regional Administrator, Region IV, may, in writing, relax or rescind any of the above conditions upon demonstration by the Licensee of good cause.
In accordance with 10 CFR 2.202, the Licensee must, and any other person adversely affected by this Order may, submit an answer to this Order within 20 days of its issuance. In addition, the Licensee and any other person adversely affected by this Order may request a hearing on this Order within 20 days of its issuance. Where good cause is shown, consideration will be given to extending the time to answer or request a hearing. A request for extension of time must be directed to the Director, Office of Enforcement, U.S. Nuclear Regulatory Commission, and include a statement of good cause for the extension.
A request for a hearing must be filed in accordance with the NRC E Filing rule, which the NRC promulgated in August 2007, 72 FR 49139 (Aug. 28, 2007). The EFiling process requires participants to submit and serve documents over the Internet or, in some cases, to mail copies on electronic optical storage media. Participants may not submit paper copies of their filings unless they seek a waiver in accordance with the procedures described below.
To comply with the procedural requirements associated with E
Filing, at least five (5) days prior to the filing deadline the
requestor must contact the Office of the Secretary by email at
HEARINGDOCKET@NRC.GOV, or by calling (301) 4151677, to request (1) a
digital ID certificate, which allows the participant (or its counsel or
representative) to digitally sign documents and access the ESubmittal
server for any NRC proceeding in which it is participating; and/or (2)
creation of an electronic docket for the proceeding (even in instances
when the requestor (or its counsel or representative) already holds an
NRCissued digital ID certificate). Each requestor will need to
download the Workplace Forms ViewerTM to access the Electronic
[[Page 50655]]
Information Exchange (EIE), a component of the EFiling system. The
Workplace Forms ViewerTM is free and is available at http://
www.nrc.gov/sitehelp/esubmittals/installviewer.html. Information
about applying for a digital ID certificate also is available on NRC's
public Web site at http://www.nrc.gov/sitehelp/esubmittals/apply certificates.html.
Once a requestor has obtained a digital ID certificate, had a docket created, and downloaded the EIE viewer, it can then submit a request for a hearing through EIE. Submissions should be in Portable Document Format (PDF) in accordance with NRC guidance available on the NRC public Web site at http://www.nrc.gov/sitehelp/esubmittals.html. A filing is considered complete at the time the filer submits its document through EIE. To be timely, electronic filings must be submitted to the EIE system no later than 11:59 p.m. Eastern Time on the due date. Upon receipt of a transmission, the EFiling system time stamps the document and sends the submitter an email notice confirming receipt of the document. The EIE system also distributes an email notice that provides access to the document to the NRC Office of the General Counsel and any others who have advised the Office of the Secretary that they wish to participate in the proceeding, so that the filer need not serve the document on those participants separately. Therefore, any others who wish to participate in the proceeding (or their counsel or representative) must apply for and receive a digital ID certificate before a hearing request is filed so that they may obtain access to the document via the EFiling system.
A person filing electronically may seek assistance through the ``Contact Us'' link located on the NRC Web site at http://www.nrc.gov/ sitehelp/esubmittals.html or by calling the NRC technical help line, which is available between 8:30 a.m. and 4:15 p.m., Eastern Time, Monday through Friday. The help line number is (800) 3974209 or locally, (301) 4154737.
Participants who believe that they have good cause for not submitting documents electronically must file a motion, in accordance with 10 CFR 2.302(g), with their initial paper filing requesting authorization to continue to submit documents in paper format. Such filings must be submitted by (1) first class mail addressed to the Office of the Secretary of the Commission, U.S. Nuclear Regulatory Commission, Washington, DC 205550001, Attention: Rulemaking and Adjudications Staff; or (2) courier, express mail, or expedited delivery service to the Office of the Secretary, Sixteenth Floor, One White Flint North, 11555 Rockville Pike, Rockville, Maryland 20852, Attention: Rulemaking and Adjudications Staff. Participants filing a document in this manner are responsible for serving the document on all other participants. Filing is considered complete by firstclass mail as of the time of deposit in the mail, or by courier, express mail, or expedited delivery service upon depositing the document with the provider of the service.
Documents submitted in adjudicatory proceedings will appear in NRC's electronic hearing docket which is available to the public at http://ehd.nrc.gov/EHD_Proceeding/home.asp, unless excluded pursuant to an order of the Commission, an Atomic Safety and Licensing Board, or a Presiding Officer. Participants are requested not to include personal privacy information, such as social security numbers, home addresses, or home phone numbers in their filings. With respect to copyrighted works, except for limited excerpts that serve the purpose of the adjudicatory filings and would constitute a Fair Use application, Participants are requested not to include copyrighted materials in their works.
If a person other than the Licensee requests a hearing, that person shall set forth with particularity the manner in which his interest is adversely affected by this Order and shall address the criteria set forth in 10 CFR 2.309(d).
If a hearing is requested by a Licensee or a person whose interest is adversely affected, the Commission will issue an Order designating the time and place of any hearings. If a hearing is held, the issue to be considered at such hearing shall be whether this Order should be sustained. Pursuant to 10 CFR 2.202(c)(2)(i), the Licensee, or any other person adversely affected by this Order, may, in addition to demanding a hearing, at the time the answer is filed or sooner, move the presiding officer to set aside the immediate effectiveness of the Order on the ground that the Order, including the need for immediate effectiveness, is not based on adequate evidence but on mere suspicion, unfounded allegations, or error. In the absence of any request for hearing, or written approval of an extension of time in which to request a hearing, the provisions specified in Section IV above shall be final 20 days from the date of this Order without further order or proceedings. If an extension of time for requesting a hearing has been approved, the provisions specified in Section IV shall be final when the extension expires if a hearing request has not been received.
An answer or a request for hearing shall not stay the immediate effectiveness of this order.
Dated this 20th day of August 2008.
For the Nuclear Regulatory Commission.
Cynthia A. Carpenter,
Director, Office of Enforcement.
[FR Doc. E819831 Filed 82608; 8:45 am]
BILLING CODE 759001P
SUMMARY: Alaska Industrial X-Ray, Inc.,
DOCUMENT BODY 2: I
Alaska Industrial XRay, Inc. (AIX or Licensee) is the holder of Materials License No. 501608401 issued by the Nuclear Regulatory Commission (NRC or Commission) pursuant to 10 CFR Parts 3036, 39, 40, and 70 and last amended on November 2, 2007, and due to expire on March 31, 2011. The license authorizes AIX to possess and use sealed radioactive sources in conducting industrial radiography activities in accordance with the conditions specified therein.
In June 2007, the NRC conducted an onsite inspection and began an investigation into AIX activities to determine whether deliberate violations of NRC requirements occurred. During the investigation, the NRC discovered that AIX radiographers had conducted radiography activities in violation of 10 CFR 34.41(a) on multiple occasions at the Arctic Slope Regional Corporation Energy Services (ASRC) site and the Golovin site, both temporary jobsites. Of concern is that the NRC previously had issued an identical violation of 10 CFR 34.41(a) involving deliberate misconduct at the ASRC site on April 25, 2001 (EA 01015). Based on the preliminary information from the investigation, the NRC issued an Order Suspending Licensed Activities (EA07261) on October 19, 2007, which, among other conditions, required that AIX suspend its radiography activities until adequate assurance could be provided by independent means that AIX would comply with NRC requirements when conducting licensed activities. On November 8, 2007, the NRC relaxed the Order based on several actions taken and commitments made by AIX to the NRC. The Order was a temporary measure while the NRC completed its investigation and reviewed the results. Once completed, the results of the inspection and investigation were discussed with AIX during a telephonic exit briefing on April 23, 2008, and were documented in NRC Inspection Report No. 03010346/0701 dated May 20, 2008.
On June 5, 2008, a predecisional enforcement conference (PEC) was [[Page 50652]]
conducted with AIX in Anchorage, Alaska, to discuss with the company
and its employees the apparent violations, their significance, their
root causes, and any corrective actions. The individuals of concern
included two fulltime radiographers, a parttime radiographer, and the
former radiation safety officer (RSO) who, at the time of the PEC, was
employed by AIX as a fulltime radiographer. During the PEC, the four
individuals admitted to committing deliberate violations of 10 CFR
34.41(a) at the ASRC site on multiple occasions over a period of
several years. This information was substantively consistent with their
sworn statements provided to the NRC Office of Investigations. Based on
the investigation, the NRC concluded that this violation had occurred
on multiple occasions from about 2004 until the investigation in June 2007.
In addition, during the PEC, the NRC staff discussed with the president of AIX that during his first interview on July 24, 2007, he denied that violations of the twoperson rule had occurred at the ASRC site. Later, on July 25, 2007, when confronted with information that showed that his radiographers had indeed deliberately violated the two person rule at the ASRC site, the company president stated that he suspected violations of the twoperson rule had occurred at the ASRC site, but took no action to investigate his suspicions or discuss this with his personnel. As a result, the NRC has concluded that the AIX president, with careless disregard, provided the NRC with information about the company that was incomplete or inaccurate, in violation of 10 CFR 30.9(a).
During the PEC, the NRC noted that in 2001 it had issued a Severity
Level III violation of 10 CFR 34.41(a) to AIX for deliberate failures
to follow the twoperson rule at the ASRC site.\1\ The fact that a
prior enforcement action had been issued for the same violation at the
same location was a significant concern to the NRC because it raised
questions about the effectiveness of AIX management oversight to
prevent recurrence of violations.\2\ In fact, a few years later in
about 2004, the former AIX RSO, and almost all of AIX's radiographers
and assistant radiographers who worked at the ASRC site, began
deliberately failing to follow the twoperson rule at the ASRC site.
Further, the reason the violations reoccurred in 20042007 were very
similar to the reasons the violations occurred in 2001: The
radiographers felt that oneperson radiography was safe at the ASRC
site, and following the twoperson rule was unnecessary because
radiographic exposures were performed inside a structure that AIX had
built prior to 2001, intended to meet NRC specifications for a permanent radiographic installation.\3\
\1\ On April 25, 2001, the NRC issued a Notice of Violation for
a Severity Level III violation involving a failure to meet the requirements of 10 CFR 34.41(a) (EA01015).
\2\ As part of the corrective actions for the 2001 violation
involving deliberate failures to follow the twoperson rule at the
ASRC site, the AIX company president, its former RSO, and all
radiographers and assistant radiographers signed a memorandum, in
February 2001, acknowledging that the twoperson rule was to be
followed at the ASRC site. A copy of the memorandum was presented to the NRC in March 2001.
\3\ In 20012002, AIX had requested that the NRC approve the
structure it had built at the ASRC site as a permanent radiographic installation. However, the structure required extensive
modifications in order to meet NRC requirements. AIX did not make
the modifications and, as a result, the NRC never approved it. If
the structure had been approved, then AIX would have been authorized
to conduct radiography with only one individual instead of two.
During the PEC, the company president stated that he could understand why AIX personnel failed to follow the twoperson rule and that he (the company president) might have done it himself if he were conducting radiography. One of the reasons for this was the general belief that the structure provided a similar level of protection as a permanent radiographic installation.
The company president stated that he ``probably suspected'' that AIX radiographers were not abiding by the twoperson rule, but that he ``never went [to the ASRC site] and tried to catch anybody at it.'' Thus, NRC representatives also questioned AIX regarding the lack of management oversight from both the former AIX RSO and the company president.
In addition to the deliberate violations of 10 CFR 34.41(a) and the willful violation of 10 CFR 30.9(a), the NRC representatives noted three additional concerns during the June 2008 PEC. First, during a tour of the ASRC site, the day prior to the June 5th conference, the two trailers which formed the sides of the structure were found to be unlocked and open. This was of concern to the NRC staff because of the potential that ASRC personnel (considered members of the public for purposes of the regulations) might access the trailers during radiography and be exposed to radiation or remove some of the trailer contents, which could reduce the level of shielding. In addition, this undermined NRC's confidence in AIX to meet its commitments because in its letter dated November 1, 2007, AIX committed to keep the trailers locked and to control access to the trailers. This commitment was made to the NRC as a consideration for lifting the Order Suspending License dated October 19, 2007. On June 4, 2008, the NRC staff requested that AIX review the issue and provide additional assurance it would meet its commitments to the NRC. Second, the NRC staff was concerned that radiation streaming could occur through the back of the structure because there was an opening in between the two trailers which formed the back of the structure. The staff questioned whether radiation surveys were conducted to establish that the radiation rope boundaries were adequate. This was important because of the possibility that ASRC personnel (considered members of the public) might at times be present behind the structure and could be exposed to radiation areas in excess of NRC limits. And third, the NRC staff noted that although the focus of the June 5th PEC was deliberate violations associated with radiography at the ASRC site, other examples of failures to comply with 10 CFR 34.41(a) were identified at AIX's Golovin site. Although the NRC did not find any deliberate misconduct associated with the 10 CFR 34.41(a) violations at the AIX Golovin site, corrective actions were needed to correct the violations at that site.
AIX's corrective actions presented at the June 5th PEC included: (1) Continuing to contract with an independent contractor to conduct inspections of AIX radiographers, as AIX committed in response to the NRC's Order Suspending Licensed Activities (EA07261) dated October 19, 2007; (2) changing the RSO in November 2007; (3) reducing the number of radiographic exposures at the Golovin site with NRClicensed material; (4) modifying contractual agreements with ASRC to reduce schedule pressures and to ensure compliance with 10 CFR 34.41(a); and (5) instituting a disciplinary policy to terminate any radiographer who did not follow the twoperson rule. The NRC representatives also discussed concerns about whether the independent oversight was as effective as it could or should be.
These corrective actions did not address the NRC's concerns about
AIX's lack of management oversight in AIX's radiography activities
including the failure to ensure that its employees, including the
former AIX RSO, were following NRC requirements, despite the company
president's suspicions that violations were occurring, as well as the
fact that corrective actions for the 2001 enforcement action were not
effective. As a result, the NRC representatives provided AIX with more time to provide
[[Page 50653]]
any additional corrective actions. By letter dated June 9, 2008, AIX
provided additional corrective actions which included: (1) Conducting
monthly safety meetings; (2) a commitment from the company president to
independently and personally review (audit) each crew on a quarterly
basis at a minimum; (3) performing surveys around the ASRC radiation
exposure area, where instantaneous dose rates were found to exceed 20
millirem/hour in several areas, and AIX applying additional dirt
(shielding) to the perimeter of the structure; and (4) locking and
rebolting the doors to the trailers at the ASRC site which AIX uses as
shielding around the area where radiographic exposures are performed.
In summary, based on the information developed during the inspection, the investigation, and the PEC, the NRC has determined that two violations of NRC requirements occurred. These violations are cited in the enclosed Notice of Violation and Proposed Imposition of Civil Penalty (Notice) dated the same day as this Order, and the circumstances surrounding them are described in detail in the subject inspection report and the cover letter accompanying this Order. The violations involve: (1) Performing radiography at a location other than a permanent radiographic installation without the presence of two qualified individuals, in violation of 10 CFR 34.41(a), and (2) failing to provide the NRC with information that was complete and accurate in all material respects, in violation of 10 CFR 30.9(a). The NRC has determined that willfulness was associated with both violations.
In assessing the safety significance of the violations, the NRC notes that, absent deliberate misconduct, performing radiography in violation of the twoperson rule is significant because the use of two qualified persons during radiographic operations not only provides for a high level of assurance that members of the public will be prevented from entering the restricted area during those operations, but also provides additional protection for the radiographers should one of them become incapacitated while the source is unshielded. The second violation, providing the NRC with incomplete or inaccurate information, impacts the NRC's ability to perform its regulatory function. The violations were more significant given the pervasive deliberate misconduct on the part of the AIX radiographers and assistant radiographers, as well as a senior company official, the RSO at the time; and the careless disregard on the part of the president of the company, in providing the NRC with information that was incomplete or inaccurate. Therefore, these violations have been categorized in accordance with the NRC Enforcement Policy at Severity Level II.
The NRC has determined that additional actions \4\ are needed to
provide reasonable assurance that the public health and safety, as well
as the health and safety of AIX employees, will be maintained. The
circumstances in this case raise serious concerns about AIX company
management's ability or desire to ensure licensed activities are
conducted without undue risk to the public's health and safety, and
that commitments made to the NRC are honored. Therefore, the NRC is
issuing an Order to require (1) Continued independent oversight with
additional specific conditions to ensure AIX's radiographers follow NRC
requirements, (2) that the trailers be locked and that AIX maintain
control over the key, (3) that AIX contract with an independent
consultant to evaluate the AIX radiation safety procedures for
effectiveness, and to provide training to AIX radiographers and
assistant radiographers, and (4) that the president of AIX, perform quarterly audits of your radiographers.
\4\ These actions are in addition to, and separate from, the
attached Notice, which imposes a civil penalty at twice the base for
the Severity Level II problem in the total amount of $20,800. As
fully set out in the Notice, the civil penalty was issued to
emphasize the importance of not engaging in deliberate misconduct,
selfidentifying violations, and taking prompt and comprehensive corrective actions.
Based on the above, the NRC has determined that AIX company management, including the company president, have not provided the level of oversight needed for the company to conduct its activities in compliance with NRC requirements and to meet all its commitments to the NRC. Consequently, I lack the requisite reasonable assurance that the Licensee's current operations can be conducted under License No. 50 1608401 in compliance with the Commission's requirements and that the health and safety of the public, including the Licensee's employees, will be protected. Therefore, the public health and safety interest require that License No. 501608401 be modified to require additional actions so as to provide reasonable assurance that the health and safety of the public will be protected. Furthermore, pursuant to 10 CFR 2.202, I find that the significance of the violations described above is such that the public health and safety interest require that this Order be immediately effective.
Accordingly, pursuant to Sections 81, 161b, 161i, 161o, 182, and
186 of the Atomic Energy Act of 1954, as amended, the Commission's
regulations in 10 CFR 2.202, 2.205, 10 CFR parts 20, 34, and 10 CFR
150.20, it is hereby ordered, effective immediately, that License No. 501608401 is modified as follows:
(1) AIX shall continue use of an independent contractor to provide independent oversight of AIX operations.
(a) AIX shall notify the NRC by fax and the contractor documented
in AIX's letter dated November 1, 2007, by phone, fax or email, on a
weekly basis, of the anticipated AIX work schedule for that week. AIX
will immediately notify the contractor daily, by phone, fax and or
email, as requested by the contractor, of any changes to AIX scheduled
activities. AIX must inform the contractor in writing that the provisions of 10 CFR 30.10 apply to the contractor.
(b) The contractor must conduct unannounced audits and observations
of AIX radiography crews during radiographic exposures in a manner and
location where he is undetected by the radiography crew. After
observing the crews, the contractor may announce himself to the crew in
order to complete his audits of the jobsite. The audits must verify
that AIX personnel are conducting all operations in a safe manner and
in compliance with NRC requirements. The contractor must, to the extent
possible, prevent violations from occurring or continuing as he
observes the radiography crews, even in situations where the crew has not detected his presence prior to the violation.
(c) The unannounced audits shall be conducted at least twice a month when work is being performed.
(d) At least 50 percent of the time, on average over a year, the
contractor must conduct unannounced audits during the second half of
work that is scheduled outside of normal business hours. Normal business hours are 8 a.m. to 5 p.m.
(e) The contractor will provide AIX a monthly report of his audit
activities. The information will be provided to NRC Region IV at the
same time the contractor provides the results to AIX. At a minimum, the
information provided shall include: The date and times of the audit;
the hours (time of the day) in which the crew worked; the names of the
radiographers and assistant radiographers involved in the work; [[Page 50654]]
whether the contractor was detected by the crew prior to the contractor
announcing his presence; and whether or not radiographic operations
were performed safely and in compliance with NRC requirements. The
monthly reports will be sent to the Director, Division of Nuclear Materials Safety, U.S. NRC Region IV.
(f) Individuals with whom AIX contracts to meet this requirement,
must be approved in advance. AIX currently contracts with an individual
who has received prior approval and further approval for this
individual is not needed. In order to receive prior approval for
another individual to perform these independent audits, AIX must
provide the NRC with information regarding the individual's
qualifications and information concerning any prior working
relationships the individual has had with AIX. This information should
be sent to the Director, Division of Nuclear Materials Safety, U.S. NRC Region IV.
(2) The trailers that surround the radiographic site at ASRC will
be locked during the conduct of radiography. AIX must maintain control
over the key such that ASRC personnel cannot obtain the key without the AIX company management's approval.
(3) AIX will contract with an independent consultant to evaluate
the effectiveness of its radiation safety and compliance programs.
(a) Within 60 days of the date of this Order, AIX will submit to
the NRC for approval, the name(s) and qualifications of an independent
consultant to review and evaluate AIX's radiation safety program and compliance program;
(b) Within 30 days of NRC approval of the consultant, the
consultant will commence an assessment of AIX's radiation safety program;
(c) The consultant's assessment will review AIX's training program as follows:
(i) Physical observation of each of AIX's radiographers and
assistant radiographers, on multiple occasions, during the conduct of
radiographic operations, verifying their actions ensure radiation
safety and compliance with NRC requirements. At least 25 percent of the
observations will be conducted at the ASRC site. The purpose of the
observation is to evaluate compliance with NRC requirements and to
provide recommendations to AIX management about improving the work
practices of AIX radiographers to comply with NRC requirements. The
consultant should consider providing recommendations to AIX for
complying with NRC requirements during inclement weather (e.g., winter conditions) during radiographic operations.
(ii) Perform independent radiation measurements around AIX's
structure used at the ASRC site, taking into account changes in the
shielding characteristics as material inside the trailers that form the
walls of the structure vary. The purpose of the measurements will be to demonstrate compliance with 10 CFR part 20 limits.
(iii) Evaluate AIX's Operating and Emergency Procedures.
(iv) Evaluate the effectiveness of the current AIX RSO to oversee
the AIX radiation safety program and to ensure compliance with NRC requirements;
(v) Within 30 days following completion of its reviews, the
consultant will provide AIX a report discussing its findings and
recommendations for program improvements. At the same time the
consultant provides its report to AIX, the consultant will send a copy
to the Director, Division of Nuclear Material Safety, U.S. NRC Region IV.
(d) Within 30 days of receiving the consultant's report, AIX will
provide the NRC, in writing, its position on how it will address the
consultant's findings. In its correspondence to the NRC, AIX will
identify which of the consultant's recommendations it will implement
and the time frame in which it will implement the recommendations. For
those recommendations AIX does not accept, AIX will provide the NRC with its justification.
(e) The consultant will provide training to all AIX employees, managers, and officials. The training will include:
(i) A review of the radiation mishaps involving radiography devices or gauges;
(ii) A review of the potential actions that NRC may take against an individual;
(iii) A review of NRC requirements, AIX's license conditions; and
(iv) A review of AIX's Operating and Emergency Procedures.
(4) The president of AIX shall perform quarterly audits of his
radiographers as they conduct radiography. The audits shall include
observations of his crew during radiographic exposures and, to the
extent possible, must include observations such that the crew cannot
detect his presence. At least 25 percent of the observations will be
conducted at the ASRC site during the second half of work that is
scheduled outside of the normal business hours of 8 a.m. to 5 p.m. The
president of AIX must, to the extent possible, prevent violations from
occurring or continuing as he observes the radiography crews, even in
situations where the crew has not detected his presence prior to the
violation. These audits must be separate and apart from any required
audits performed for compliance with 10 CFR 34.43(e). Records shall be
maintained documenting these audits and the results of his observations.
(5) Information that is required to be sent to the NRC in
Conditions 14 above shall be addressed to: Director, Division of
Nuclear Materials Safety, U.S. NRC Region IV; 612 East Lamar Blvd., Suite 400, Arlington, TX 76011.
The Regional Administrator, Region IV, may, in writing, relax or rescind any of the above conditions upon demonstration by the Licensee of good cause.
In accordance with 10 CFR 2.202, the Licensee must, and any other person adversely affected by this Order may, submit an answer to this Order within 20 days of its issuance. In addition, the Licensee and any other person adversely affected by this Order may request a hearing on this Order within 20 days of its issuance. Where good cause is shown, consideration will be given to extending the time to answer or request a hearing. A request for extension of time must be directed to the Director, Office of Enforcement, U.S. Nuclear Regulatory Commission, and include a statement of good cause for the extension.
A request for a hearing must be filed in accordance with the NRC E Filing rule, which the NRC promulgated in August 2007, 72 FR 49139 (Aug. 28, 2007). The EFiling process requires participants to submit and serve documents over the Internet or, in some cases, to mail copies on electronic optical storage media. Participants may not submit paper copies of their filings unless they seek a waiver in accordance with the procedures described below.
To comply with the procedural requirements associated with E
Filing, at least five (5) days prior to the filing deadline the
requestor must contact the Office of the Secretary by email at
HEARINGDOCKET@NRC.GOV, or by calling (301) 4151677, to request (1) a
digital ID certificate, which allows the participant (or its counsel or
representative) to digitally sign documents and access the ESubmittal
server for any NRC proceeding in which it is participating; and/or (2)
creation of an electronic docket for the proceeding (even in instances
when the requestor (or its counsel or representative) already holds an
NRCissued digital ID certificate). Each requestor will need to
download the Workplace Forms ViewerTM to access the Electronic
[[Page 50655]]
Information Exchange (EIE), a component of the EFiling system. The
Workplace Forms ViewerTM is free and is available at http://
www.nrc.gov/sitehelp/esubmittals/installviewer.html. Information
about applying for a digital ID certificate also is available on NRC's
public Web site at http://www.nrc.gov/sitehelp/esubmittals/apply certificates.html.
Once a requestor has obtained a digital ID certificate, had a docket created, and downloaded the EIE viewer, it can then submit a request for a hearing through EIE. Submissions should be in Portable Document Format (PDF) in accordance with NRC guidance available on the NRC public Web site at http://www.nrc.gov/sitehelp/esubmittals.html. A filing is considered complete at the time the filer submits its document through EIE. To be timely, electronic filings must be submitted to the EIE system no later than 11:59 p.m. Eastern Time on the due date. Upon receipt of a transmission, the EFiling system time stamps the document and sends the submitter an email notice confirming receipt of the document. The EIE system also distributes an email notice that provides access to the document to the NRC Office of the General Counsel and any others who have advised the Office of the Secretary that they wish to participate in the proceeding, so that the filer need not serve the document on those participants separately. Therefore, any others who wish to participate in the proceeding (or their counsel or representative) must apply for and receive a digital ID certificate before a hearing request is filed so that they may obtain access to the document via the EFiling system.
A person filing electronically may seek assistance through the ``Contact Us'' link located on the NRC Web site at http://www.nrc.gov/ sitehelp/esubmittals.html or by calling the NRC technical help line, which is available between 8:30 a.m. and 4:15 p.m., Eastern Time, Monday through Friday. The help line number is (800) 3974209 or locally, (301) 4154737.
Participants who believe that they have good cause for not submitting documents electronically must file a motion, in accordance with 10 CFR 2.302(g), with their initial paper filing requesting authorization to continue to submit documents in paper format. Such filings must be submitted by (1) first class mail addressed to the Office of the Secretary of the Commission, U.S. Nuclear Regulatory Commission, Washington, DC 205550001, Attention: Rulemaking and Adjudications Staff; or (2) courier, express mail, or expedited delivery service to the Office of the Secretary, Sixteenth Floor, One White Flint North, 11555 Rockville Pike, Rockville, Maryland 20852, Attention: Rulemaking and Adjudications Staff. Participants filing a document in this manner are responsible for serving the document on all other participants. Filing is considered complete by firstclass mail as of the time of deposit in the mail, or by courier, express mail, or expedited delivery service upon depositing the document with the provider of the service.
Documents submitted in adjudicatory proceedings will appear in NRC's electronic hearing docket which is available to the public at http://ehd.nrc.gov/EHD_Proceeding/home.asp, unless excluded pursuant to an order of the Commission, an Atomic Safety and Licensing Board, or a Presiding Officer. Participants are requested not to include personal privacy information, such as social security numbers, home addresses, or home phone numbers in their filings. With respect to copyrighted works, except for limited excerpts that serve the purpose of the adjudicatory filings and would constitute a Fair Use application, Participants are requested not to include copyrighted materials in their works.
If a person other than the Licensee requests a hearing, that person shall set forth with particularity the manner in which his interest is adversely affected by this Order and shall address the criteria set forth in 10 CFR 2.309(d).
If a hearing is requested by a Licensee or a person whose interest is adversely affected, the Commission will issue an Order designating the time and place of any hearings. If a hearing is held, the issue to be considered at such hearing shall be whether this Order should be sustained. Pursuant to 10 CFR 2.202(c)(2)(i), the Licensee, or any other person adversely affected by this Order, may, in addition to demanding a hearing, at the time the answer is filed or sooner, move the presiding officer to set aside the immediate effectiveness of the Order on the ground that the Order, including the need for immediate effectiveness, is not based on adequate evidence but on mere suspicion, unfounded allegations, or error. In the absence of any request for hearing, or written approval of an extension of time in which to request a hearing, the provisions specified in Section IV above shall be final 20 days from the date of this Order without further order or proceedings. If an extension of time for requesting a hearing has been approved, the provisions specified in Section IV shall be final when the extension expires if a hearing request has not been received.
An answer or a request for hearing shall not stay the immediate effectiveness of this order.
Dated this 20th day of August 2008.
For the Nuclear Regulatory Commission.
Cynthia A. Carpenter,
Director, Office of Enforcement.
[FR Doc. E819831 Filed 82608; 8:45 am]
BILLING CODE 759001P
14 CFR Part 39 40 CFR Part 52 14 CFR Part 71 33 CFR Part 165 50 CFR Part 679 47 CFR Part 73 26 CFR Part 1 40 CFR Part 180 33 CFR Part 117 50 CFR Part 17 44 CFR Part 67 50 CFR Part 648 14 CFR Part 97 33 CFR Part 100 40 CFR Part 63 50 CFR Part 622 44 CFR Part 65 50 CFR Part 660 26 CFR Part 301 39 CFR Part 111 40 CFR Part 300 6 CFR Part 5 40 CFR Part 271 47 CFR Part 64 40 CFR Parts 52 and 81 50 CFR Part 665 44 CFR Part 64 10 CFR Part 50 49 CFR Part 571 47 CFR Part 76